New York City, New York · Battery storage
Leasing land for battery storage near a New York City subway
Sources checked
When transit approval is required
New York City Building Code § 3304.3.5 requires approval from the transit authority with jurisdiction when excavation of any depth is proposed within 200 feet of its property or infrastructure. For private construction near MTA property, ask the developer to document its review with the MTA External Partner Program before you commit to a layout or construction date.
A battery enclosure can fit on your lot while a cable trench or foundation brings the work within 200 feet of a tunnel or other transit asset. Ask for a drawing that shows the whole job, including the work needed to connect and deliver the batteries.
Check the full construction plan
The 200-foot provision covers facilities, infrastructure and property under the New York City Transit Authority, the Metropolitan Transportation Authority and the Port Authority of New York and New Jersey. Identify the authority responsible for each feature near the work. If your plan shows Port Authority property, ask the Port Authority what it requires. For an owner’s project near MTA or NYCT property, use the MTA’s private Adjacency process.
Give the developer your street address, borough, tax block and lot, and any survey or recorded transit easement you have. Ask for a dated plan that shows the battery and transformer pads, footing and fence work, cable routes to the point of connection, and temporary work areas. The same drawing should show where each proposed excavation starts and ends, including street work the utility may perform.
Use a subway map or a nearby station entrance as a clue. Ask the project team to verify the distance using the actual transit structures and property, with a New York-licensed surveyor where needed. The External Partner Program directs private owners to apply for construction activity within 200 feet of MTA assets and asks for details of temporary equipment loads. Have the team flag proposed battery delivery and crane staging even when the pads sit outside the initial review area.
Sources NYC Building Code § 3304.3.5, transit authority approval for excavation · MTA External Partner Program General Notes, revision 3, May 2026 · MTA External Partner Program FAQ, private Adjacency applications
Get the transit drawings and a written decision
Have the developer’s design professional request MTA archival drawings and verify their information against the site survey. The archive request identifies the project, location and nearby subway line or station. For the private Adjacency submission through EPIC, the design team overlays the MTA records on its signed and sealed engineering drawings in plan and cross section. Compare the drawing numbers and dates with the plan attached to your land agreement.
Ask for the application number and the written MTA disposition covering the scope you reviewed. The MTA’s General Notes distinguish a No Impact disposition from Approved or Approved as Noted drawings. For the approval path, the MTA requires an executed agreement, approved insurance and minimum safety requirements before it issues a Notice to Proceed.
Track Department of Buildings and FDNY approvals on the same project schedule. The FDNY installation guide sets out its equipment and installation review and states that indoor and outdoor energy storage systems require DOB approval and a work permit. The Building Code also requires the owner or contractor to notify the relevant transit authority before excavation covered by § 3304.3.5.
Sources MTA Archive Information Request Form · MTA External Partner Program, EPIC application portal · MTA External Partner Program General Notes, revision 3, May 2026 · FDNY Energy Storage System Equipment Approval and Installation Guide · NYC Building Code § 3304.3.5, transit authority approval for excavation
Decide what the developer can do next
Compare each piece of evidence with the current drawing before you grant additional site rights. These examples show how the answer can change during an option period.
| What the developer shows | What to ask for |
|---|---|
| The battery pad sits 240 feet from the surveyed MTA property. A proposed conduit trench comes within 145 feet. | Ask for the transit review to cover the trench and identify who will file for the utility’s portion of the work. |
| A No Impact letter covers the original layout. The new layout moves the transformer foundation toward the subway. | Ask the developer to show the revision to EPP and obtain its written direction on an addendum or other updated review. |
| MTA stamped the plans Approved as Noted. The developer wants to bring in construction equipment. | Ask for the Notice to Proceed and evidence the applicable city permits are in place. Check who will coordinate any MTA inspections. |
| The battery pads and trenches are beyond the measured 200 feet. The contractor may need to pump groundwater during construction. | Ask EPP about the dewatering scope. Its FAQ identifies dewatering as a reason to apply even beyond 200 feet. |
Sources NYC Building Code § 3304.3.5, transit authority approval for excavation · MTA External Partner Program General Notes, revision 3, May 2026 · MTA External Partner Program FAQ, private Adjacency applications
Put the review milestone in the land agreement
If you are offering an option, start with a deadline for the developer to bring you a survey-backed plan and identify the authority and filing lead for each part of the work. If the option can be extended for MTA review, ask what the developer must show to qualify for the extension, when the extension ends and what the developer pays for it.
Before construction access starts, ask your adviser to tie it to the written transit disposition and permits for the agreed plan. For work requiring an MTA Notice to Proceed, include it in that milestone. Keep any early entry permission specific to the survey or testing you agree to and require the project team to secure approvals that apply to intrusive testing.
Ask who signs and pays for any MTA agreement, insurance, engineered protection and monitoring. If the developer needs a different trench, delivery route or temporary work area on land you retain, have it bring you the revised plan and applicable agency decisions before using the additional area. If the approved layout leaves too little usable space, use the option’s agreed deadline and release terms to decide whether to free the acreage for another use.
Sources MTA External Partner Program General Notes, revision 3, May 2026 · MTA External Partner Program FAQ, private Adjacency applications
Common questions
Is 200 feet a minimum setback for the batteries?
Section 3304.3.5 uses 200 feet to trigger transit authority approval for excavation. The authority reviews the scope and layout for the particular site.
Does a shallow cable trench count?
The code applies to excavation of any depth within 200 feet of covered transit property or infrastructure. Have the design team include shallow trenches and confirm which authority reviews them.
Which document should I ask to see after MTA review?
Ask for the written disposition and the list of drawing revisions it covers. If MTA approved the drawings or approved them as noted, also ask for the Notice to Proceed before releasing construction access.
Who handles review for a utility’s connection work?
Ask the developer for a written scope split with the utility. The MTA has a Public Agency or Utility Project application category, so confirm with EPP which party files for each part and get both schedules before you set a construction date.
Sources
The EPIC portal directs applicants to the May 2026 General Notes. Use those notes and the current EPIC forms when checking the project’s review status and conditions.
- NYC Building Code § 3304.3.5, transit authority approval for excavation
- MTA External Partner Program General Notes, revision 3, May 2026
- MTA External Partner Program FAQ, private Adjacency applications
- MTA External Partner Program, EPIC application portal
- MTA Archive Information Request Form
- FDNY Energy Storage System Equipment Approval and Installation Guide