Two Rivers, Wisconsin · Battery storage

When could Two Rivers review plans for the Hawk battery project?

Sources checked

Hawk needed the purchase option before plan review

Two Rivers approved Hawk’s conditional use permit in March 2024. Condition 21 required Swift Energy Storage to assign its purchase option to Hawk Energy Storage with City Council approval before the permit could take effect or the City could review plans under it. If the company named on your permit differs from the one holding the land option, ask for the signed assignment and any required consent before treating plan review as underway.

The developer named in a zoning decision may be different from the company that signed the option to buy your land. At Woodland Industrial Park in Two Rivers, Wisconsin, that difference had to be resolved before the proposed battery project could move to plan review.

Follow the three decisions in the Hawk project record

The City held the land and granted the purchase option to Swift. The City Council’s March 4, 2024 vote approved the conditional use permit with proposed conditions for Hawk. On June 17, the Council voted to grant the City’s consent to the option assignment. The June packet quotes the option’s Section 24, which required the owner’s prior written consent. The same packet includes Hawk’s written assumption of the option duties and a signature line for the City’s consent.

On July 23, the Community Development Authority and Business and Industrial Development Committee approved a preliminary site plan and a variance from the industrial park’s minimum building area requirement. Before a building permit could be issued, Hawk’s permit called for Plan Commission site and architectural plan approval as well as the applicable industrial park approvals.

Sources Two Rivers City Council, March 4, 2024 permit vote · Two Rivers Hawk conditional use permit 3-1-2024, Exhibit A conditions 17–21 · Two Rivers City Council, June 17, 2024 packet on the purchase option assignment · Two Rivers City Council, June 17, 2024 consent vote · Two Rivers, July 23, 2024 preliminary site plan and covenant variance votes

Match the option, the permit and the parcel

Use the parcel number or legal description to match the current signed option and the complete permit with exhibits. Check the exact legal name of the option holder and the company named on the permit. If those names differ, ask the developer how they will be brought into line and ask the City which document it needs before opening plan review.

What you haveWhat to request before committing
A Council vote approving a permit with conditionsGet the signed, recorded permit and its exhibits. Ask the City which conditions must be met before plan review.
Consent to the option assignmentGet the effective assignment, the new holder’s assumption of duties and any signed consent the option requires.
A preliminary plan approvalAsk for the final approval status and any separate decisions required by a recorded covenant or the permit.
A proposed option extensionGet the signed amendment and revised option deadline. Ask the City separately about any permit deadlines.

Sources Two Rivers Hawk conditional use permit 3-1-2024, Exhibit A conditions 17–21 · Two Rivers Hawk conditional use permit 3-1-2024, paragraphs 1, 2 and 6 · Two Rivers City Council, June 17, 2024 packet on the purchase option assignment · Two Rivers, July 23, 2024 preliminary site plan and covenant variance votes · Two Rivers City Council, January 20, 2025 option amendment vote

Agree on the records and dates before you sign

Start with the City Clerk for the official permit and Council actions. For a Woodland Industrial Park site, ask your title professional for the recorded declaration identified in Hawk’s permit at Volume 891, pages 402–412, plus any amendments that affect your parcel. Check the signed option and amendments for the scope and current term of the purchase right.

Keep the permit deadlines alongside the option dates. The Hawk permit called for the owner to sign and record its acceptance. Its terms also made the permit void unless the proper building and zoning use permit applications were submitted within 24 months of the permit date. In January 2025, the Council authorized signing amendments to the option and its recorded memorandum. Ask the City to confirm the current permit status, including any later filings or amendments.

  • Identify who must deliver the signed assignment and consents and when each document is due.
  • If the option would otherwise expire, state what evidence triggers an extension and what payment is due for the extra time.
  • Agree when the land is released if the deadline passes or the deal ends.

Sources Two Rivers City Clerk, official city records · Manitowoc County Register of Deeds, real estate records · Two Rivers Hawk conditional use permit 3-1-2024, Exhibit A conditions 17–21 · Two Rivers Hawk conditional use permit 3-1-2024, paragraphs 1, 2 and 6 · Two Rivers City Council, January 20, 2025 option amendment vote

Common questions

What should I ask for if the developer sends me only the vote approving the option assignment?

Ask for the signed assignment and assumption, any required owner consent and confirmation of the effective date. For a permit with a condition like Hawk’s, also ask the City what it has accepted for plan review.

Does the Hawk permit address a later transfer of the permit itself?

Yes. Paragraph 6 requires City Council authorization and a showing that the new owner can comply with the permit. Condition 21 concerns the earlier transfer of the purchase option to Hawk.

Is the Woodland Industrial Park covenant review relevant to my lot?

Check the recorded declaration and any amendments against your legal description. Ask the City which site plan approvals and variances apply to the proposed layout on that parcel.

Sources

The City’s meeting records document the Hawk permit, consent vote and preliminary plan decisions. For a current land transaction, request the executed instruments and a current permit status from the City.