Colorado · Battery storage

Battery storage well setbacks in Yuma County, Colorado

Sources checked

The 1,000-foot setback

In unincorporated Yuma County, Colorado, § 8-102(C) requires at least 1,000 feet from a covered battery energy storage system, its components and associated equipment to any water well or occupied structure, unless the property owner waives the setback in writing.

If you get a battery storage offer or learn of a project near your well, ask for a dated equipment layout and the evidence behind the well locations. Review both before agreeing to a site plan or a waiver.

What the setback covers

Yuma County’s Land Use Code applies in unincorporated areas (§ 1-105). Start with the parcel number and confirm the jurisdiction with County Land Use and Planning. Article 8 excludes systems designed and operated for a single residential household from its definition of a battery energy storage system (BESS). Section 2-102 calls for a Major Land Use Permit for utility battery storage and a Minor Land Use Permit for distributed battery storage. Ask the County which classification applies to your proposal.

The wording in § 8-102(C) covers any water well or occupied structure. Include irrigation, stock and domestic wells and potentially occupied buildings in the initial screen, even when they sit on adjoining land. The code also covers components and associated equipment. An outline around the battery containers leaves you without the information needed to check an inverter or other equipment outside that outline.

Ask the County which equipment qualifies, which structures count as occupied and what points on the equipment and the well or structure it accepts for measurement. Section 8-102(C) gives the minimum distance and written waiver provision. The County can confirm how it applies those terms to the particular layout.

Sources Yuma County Land Use Code, Article 8, §§ 8-101–8-104 · Yuma County Land Use Code, § 1-105, jurisdiction · Yuma County Land Use Code, § 2-102, permit classes

Verify the well locations

Start with the wells you or the farm operator can identify. Write down the well use, permit number if available, and the source for each location. Include wells shown in records even if you have yet to find them in the field.

In Colorado’s Well Permits search, look up a known permit number or search by geographic location. Open the permit details and any imaged documents. Compare the listed coordinates, Location Accuracy and Location Type with construction records, pump or well logs, and any plugging record. A plotted point is only as useful as its underlying location evidence.

Mark wells with conflicting or uncertain locations on the drawing. Ask the County what field verification it will accept, and have the developer identify who will arrange access and pay for the work. Flag plugged, idle, or proposed replacement wells for a specific County determination before leaving them off the screen.

Sources Colorado Division of Water Resources, Well Permits search · Colorado Division of Water Resources, well permit data dictionary

Read the equipment layout and distance table

Ask for a scaled plan with the date and revision number, north arrow, parcel lines and labeled equipment. Cross-check it against the project’s electrical diagram and equipment list. Section 8-104(A)(2) requires an electrical diagram that details the layout, components and interconnection. Section 8-104(A)(3) requires a preliminary equipment specification and a final sheet before the building permit is issued.

Have the developer list the closest relevant equipment to each well or occupied structure, the measured distance, the two measurement points and the location evidence. Keep that table with its drawing revision. The following figures are an illustration of how a single equipment move or a better location record can change the next step.

What the plan showsWhat to do
Battery enclosure 1,120 ft from a field-verified irrigation well. Inverter 960 ft from the same well.If the County counts the inverter and confirms the measurement, it falls 40 ft short. Ask for a revised layout or review the specific waiver the developer would need.
Nearest equipment 1,030 ft from a stock well pin. The source gives no reliable field location.The drawing shows 30 ft of apparent clearance. Verify the well location before relying on that margin.
Equipment moved to clear the irrigation well. The revised plan leaves the nearby house unchecked.Remeasure against the house and other relevant locations using the same revised plan.

Sources Yuma County Land Use Code, Article 8, §§ 8-101–8-104

Compare moving the equipment with signing a waiver

Ask the developer for a layout that meets the setback before comparing it with a waiver proposal. Check the equipment and access routes on both drawings. On a working farm, walk the route to the pump and controls and mark the space a service rig needs. Check whether fencing, gates, grading or cable routes would interfere with irrigation, repairs or the ability to reach a replacement well location.

If the developer requests a waiver, first ask the County which owner or owners must sign for the particular well or structure, how it wants the waiver submitted and what happens when the layout changes. If the well or structure is on adjoining land or ownership is shared, get that answer before assuming anyone can give consent.

Ask your adviser to match any proposed waiver to the specific well or structure, equipment and drawing revision. Review well access, maintenance and repair rights, who pays to verify or redesign the plan, and when a move or expansion should come back to you for review. Keep the permit consent, land agreement and waiver identifiable in the signed documents so you can tell what each signature authorized.

Sources Yuma County Land Use Code, Article 8, §§ 8-101–8-104

What to bring to County Land Use and Planning

The County uses a pre-application meeting with its Land Use Administrator to identify the permit type. If the developer has already applied, ask for the case number, the drawing revision on file, the review status and any conditions that affect the well or access. If the project has yet to be filed, bring the following to the meeting.

  • The parcel number and dated, scaled plan, with land boundaries and equipment labeled.
  • Your well list and its supporting records, including any uncertain coordinates and nearby wells or occupied buildings.
  • The measured distances on that same plan, with the points the developer used and any open questions about which equipment to include.
  • The layout that meets the setback, if available, and any alternative layout or draft waiver the developer wants you to accept.
  • A sketch of the access route and space needed to service the pump or well after the facility is built.

Section 8-104 also calls for a drainage plan and a fire mitigation plan with the information specified in the code. If the drawings change, ask how the change affects those plans as well as the setback and farm access.

Sources Yuma County Land Use and Planning, pre-application and permit review · Yuma County Land Use Code, § 8-104(A)(7)–(8), fire mitigation and drainage plans

Common questions

Does the 1,000-foot setback cover irrigation and stock wells?

Section 8-102(C) applies to any water well. Include irrigation and stock wells in the initial screen and confirm with County Land Use and Planning how it applies the code to each well you identify.

Can a well on a neighboring parcel affect the layout?

Include it in the screen. Section 8-102(C) refers to any water well without limiting the provision to wells on the project parcel. Ask the County what evidence it needs for the location and who can sign if a waiver is proposed.

What if a well map and the farm records show different locations?

Carry both locations and their sources on the drawing until the discrepancy is resolved. If the distance is near 1,000 feet or the discrepancy could change what fits, ask the County what field evidence it will accept.

Does a written waiver give the project permission to build?

A waiver addresses the setback in § 8-102(C). The County still reviews the application under the applicable permit process. Ask for the approved plan and any conditions before relying on the proposed equipment locations.

Sources

The October 2026 wind and meteorological tower amendments did not amend the battery storage provisions in Article 8.