Landowner guide

Can battery storage access or utilities cross FEMA buyout land?

A proposed route to a battery storage parcel may cross a separate lot acquired by a municipality through a FEMA flood buyout. That lot may be subject to perpetual open-space restrictions. A line on a project drawing or the municipality’s ownership does not by itself establish a right to build a road or utility crossing.

The short answer

First ask the developer to study an alignment that avoids the buyout lot. Obtain the lot’s recorded deed restrictions and any existing easements, and show the municipality the full proposed work. The municipal owner, state grant agency and FEMA need to address the applicable restrictions and any required approvals before a crossing is relied on.

Identify the lot and the proposed crossing

Ask for a preliminary drawing showing the private project parcel, the municipal lot, property lines and the proposed access and utility routes. Include temporary construction access, trenching, grading, drainage, equipment, restoration and future maintenance. A map of the general route alone may leave out work that matters to the review.

Confirm the owner and obtain the recorded deed, restrictions, survey and any existing easements from the municipality or land records. An existing corridor does not necessarily authorize a new battery project or the work shown on its plan. Have counsel and a surveyor review the actual documents and location.

Illustration of a land parcel and surrounding landscape

Understand the open-space restriction

For flood-hazard open-space acquisitions covered by 44 CFR 80.19, the property must remain open space in perpetuity to conserve natural floodplain functions. The rule generally excludes paved roads and several other uses, and limits new structures and improvements. The recorded restriction and grant documents for the particular lot also matter; FEMA’s model is a reference, not a substitute for the recorded instrument.

The regulation allows a subrecipient to convey a private easement or lease only for compatible purposes, with prior written approval of the FEMA Regional Administrator through the state and without transferring authority to control and enforce the restrictions. This is not automatic approval for a road, cable or construction activity. Other requirements or approvals may apply.

Explore a route that avoids the lot

Ask the developer to compare feasible access and utility alignments that avoid the restricted property, including their land rights, construction needs, costs and schedule. Do not treat an unpaved surface or underground installation as automatically compatible. The full work, including staging and ongoing maintenance, needs review.

If a crossing remains under consideration, ask the municipal owner to coordinate with the state grant agency and FEMA on the specific proposal, applicable deed and grant terms, compatibility and any required written approvals. Obtain their direction before assuming a route is available or work may begin.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Keep project decisions conditional on documented rights

Before signing an option or lease, ask how the developer will secure a viable route and who will pay for surveys, legal review, applications and alternatives. Have counsel review the proposed exhibits and provisions for timing, access rights and what happens if the crossing is unavailable. Flood-map status and permits for the private battery site are separate questions from rights across the buyout lot.

Sunland welcomes land and existing project inquiries nationwide. Share the property location, approximate acreage if known and your relationship to it, and mention the potential buyout-lot crossing. Provide maps and recorded documents privately if requested for review.

Questions landowners ask

Can the municipality simply grant a private easement?

Not automatically. For an acquisition covered by 44 CFR 80.19, a private easement must be for a compatible purpose and have prior written approval of the FEMA Regional Administrator through the state, among other conditions. Review the actual deed and proposal with the relevant agencies.

Does an underground utility avoid the restriction?

Not necessarily. Installation, restoration and maintenance all need to be considered against the recorded restrictions and applicable requirements. Ask the municipality to coordinate review with the state and FEMA.

Does a flood map determination for my parcel settle access?

No. The flood-map status of the private project parcel is separate from the recorded rights and restrictions governing a crossing of the buyout lot.

Sources & further reading

Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.