Identify the bridge and its posting
Mark the bridge on a map of the proposed public-road approach and record the road name, location and wording of any signs. Contact the local road agency or state transportation department to identify the bridge owner and confirm the current posting and other restrictions. Signs and restrictions can change; a map or old photograph is a starting point, not current clearance.
FHWA explains that postings can refer to gross vehicle weight, axle weight or particular vehicle configurations, and signs vary by state and locality. Ask the bridge owner to interpret the signs if unclear. Being legal on the adjoining road does not establish that a vehicle can cross the posted bridge.

Ask the developer and hauler to review the loads
Request a preliminary delivery and construction plan showing the route and expected vehicles, including loaded gross and axle weights, configurations, dimensions, and schedules. Ask the hauler to compare each proposed movement with the current restrictions and review the complete route with the responsible agencies, including any oversize or overweight permit requirements.
FHWA advises drivers not to cross when a vehicle and load exceed the posted capacity. Do not assume a general road permit authorizes a posted bridge crossing. Rules differ by jurisdiction: for example, TxDOT says TxDMV does not allow routine or superheavy overweight permits for posted bridges and describes a separate weight-tolerance permit circumstance where there is no other route. That does not establish eligibility for a particular project. Ask the responsible agency about the actual proposal rather than assuming an exception applies.
Investigate another approach before committing
If a proposed load cannot use the bridge, ask the developer and hauler to identify a route that can legally and safely carry it, or whether a different load or delivery plan is practical. Check restrictions along the whole alternative and whether it reaches an appropriate entrance. A line on a map does not establish a usable route.
Identify any separate property rights, driveway permissions or agency reviews needed for the alternative. Ask who will obtain them and pay for any necessary improvements. Have your attorney review the proposed access agreement, including responsibilities and what happens if the route or approvals are unavailable, before you grant access.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPrepare an inquiry
Sunland welcomes nationwide land and existing project inquiries. Share the property location, your relationship to it, approximate acreage if known, and the location and posted limit of the bridge if available. Provide route and access documents privately if requested for review.
Questions landowners ask
Does a public road guarantee construction truck access?
No. A bridge on the approach may have a posted limit that restricts a proposed vehicle. Have the hauler check the complete route and current restrictions.
Can an overweight permit allow a truck to cross a posted bridge?
Do not assume so. Rules and permits vary by jurisdiction and load. Ask the responsible agency and hauler about the specific bridge and movement.
Who can explain the bridge posting?
Start with the local road agency or state transportation department to identify the bridge owner, confirm the current restriction and ask how it applies.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.