Identify the premises and the people responsible
Identify the property owner, the TTB-qualified wine premises proprietor and any tenants. They may be different entities. Obtain the proprietor’s current TTB application, approved diagram and amendments, along with the deed, survey, winery lease and relevant site plans. Confirm the boundaries and uses of bonded and other wine premises with the proprietor; do not infer them from a fence, parcel map or vineyard name.
Map the proposed battery enclosures, transformers, fencing, access road, utility lines, staging and temporary construction areas against the approved diagram. Identify any overlap with wine storage, production, routes or areas needed for winery operations. A yard outside the approved premises may avoid that particular change, but construction access or utility work could still affect the premises or other rights.

Coordinate the change with the proprietor and TTB
Under 27 CFR 24.131, when a proposed change to buildings on wine premises or the use of any portion of the wine premises affects the accuracy of the application, the proprietor must submit a detailed notice to the appropriate TTB officer before making the change. The proprietor includes the change in the next required amended TTB Form 5120.25 unless the officer requires an immediate amendment. The regulation describes a notice and amendment obligation; it does not make every nearby project subject to the same filing.
TTB’s current Permits Online instructions identify a “Change in Bonded Wine Premises (extended, curtailed or modified)” amendment for changes in construction or use, including extension or curtailment of approved premises. Ask the proprietor and TTB how to describe the specific project, what updated diagram or other documents are needed, and when the area can be released for the proposed use. Do not assume that submitting a notice alone settles every issue or that the landowner can file on behalf of a separate proprietor.
Plan the transition before possession
If the yard overlaps approved premises, work with the proprietor on whether the footprint can be curtailed or modified and what must happen to wine, equipment and operations in the affected area. Show the revised boundaries and retained access clearly, and confirm any requirements concerning bonds or surety with TTB. Bond requirements depend on the proprietor’s circumstances; not every winery must maintain a bond.
Make possession, construction and other changes conditional on completing the applicable process and receiving any required approvals or confirmation. Set a realistic schedule for the proprietor’s filing and agency review. A developer’s early entry, trenching or fencing may change the use of an area before the battery equipment arrives; discuss those activities separately with the proprietor and TTB.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut the allocation in the lease
Identify the precise premises, permitted access and utility corridors, and coordinate construction with harvest, deliveries and emergency access. Specify who prepares the surveys and filings, pays costs, communicates with TTB and provides evidence that applicable requirements have been satisfied. Provide for redesign, delay or termination if the proposed change cannot be completed on acceptable terms.
Review any existing winery lease, lender or landlord consent, local land-use and fire requirements, and other agency approvals separately. An arrangement for alternating wine proprietors or for alternating between regulated alcohol operations has its own rules; it should not be assumed to authorize a third-party battery yard. Sunland welcomes battery storage land inquiries. Share the location, approximate acreage and the presence of a winery, and provide diagrams privately when needed.
Questions landowners ask
Is every vineyard part of bonded wine premises?
No. Review the proprietor’s approved application and premises diagram; ownership or proximity to a winery alone does not establish the approved boundary.
Who notifies TTB of a qualifying premises change?
Section 24.131 places the notice obligation on the proprietor. Coordinate with the actual qualified proprietor, who may be different from the landowner.
Can the developer take possession as soon as notice is filed?
Do not assume so. Ask TTB and counsel what filings, approvals or other steps apply to the specific change, and coordinate the timing before changing use or granting possession.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.