Landowner guide

Can a bonded warehouse property be handed over for battery storage?

A landlord considering battery storage at a U.S. Customs bonded warehouse may want to hand over land in phases while the tenant continues operating. Before promising access or vacant possession, identify the approved bonded area, the merchandise in it and the effect of construction on security and access.

The short answer

A lease expiration or an empty-looking area does not itself alter bonded status. Work with the bonded warehouse proprietor and U.S. Customs and Border Protection (CBP) port director to determine whether the proposed handover requires permission for an alteration, a temporary suspension or discontinuance. The proprietor must apply for the applicable change, and merchandise must be handled under CBP rules before the affected area is released. Coordinate the regulatory process with the lease and project schedule.

Map the approved bonded space and the project

Identify the bonded warehouse proprietor, warehouse class, port and site address. Obtain the current approved bonded-space plans, amendments, bond and relevant CBP correspondence from the proprietor. Compare the approved boundary with the lease premises and a current survey. A landlord and the bonded proprietor may be different parties, and property lines or a tenant’s floor plan do not necessarily establish the approved bonded boundary.

Plot each proposed handover phase, battery equipment and fencing, construction staging, access routes, underground cables, grading and utility work. Check loading doors, emergency access, security systems and the proprietor’s continuing access to merchandise and records. Ask the proprietor and port director to review the full plan before work or possession changes.

Illustration of a land parcel and surrounding landscape

Choose the right CBP process

Under 19 CFR § 19.3(a), alterations or relocation require permission from the director of the nearest port. CBP’s Bonded Warehouse Manual describes an alteration as a structural change or bonded-area change affecting security standards or regulatory requirements, and calls for a written application and blueprint. Ask CBP how the proposed boundary, access and construction changes will be treated; moving a fence or partition on a private agreement alone is not approval.

Section 19.3(b) permits the port director, on the proprietor’s written application, to temporarily suspend use of all or part of a bonded warehouse or bonded floor space for no more than one year if no bonded goods are in the affected area. CBP’s manual addresses separation for a partial suspension. Returning the area to bonded use requires the proprietor’s written application and removal of nonbonded goods, if any; approval is endorsed by the port director. This is a temporary procedure, so confirm with CBP whether it fits the project’s intended duration.

Plan discontinuance and merchandise clearance

If the proprietor wishes to discontinue the warehouse’s bonded status, § 19.3(c) calls for a written application to the port director. The regulation states that the director will not approve it until all goods in the warehouse are transferred to another bonded warehouse without expense to the government. CBP’s manual also describes withdrawal or transfer of merchandise before approval. Have the proprietor and its customs counsel confirm the appropriate lawful disposition and documentation for each inventory item with CBP; do not assume that removal from the building alone clears it.

Reestablishing a discontinued bonded warehouse requires a new application and approval under § 19.2. A temporary suspension and a permanent discontinuance are therefore different choices. Obtain the port director’s written decision and confirm the actual scope and effective timing before treating the affected area as available for construction or possession.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Reconcile goods, records and security

The proprietor should reconcile physical inventory to warehouse records, resolve discrepancies and arrange authorized withdrawals or transfers with the parties responsible for the goods. CBP describes the proprietor as liable for goods under its warehouse bond and lists several ways that liability is generally cancelled, including authorized withdrawal for consumption after duties are paid. The owner should not direct movement or disposal of someone else’s bonded merchandise without the required authority and procedures.

While operations continue, protect the bonded area and CBP access. Section 19.4 assigns the proprietor responsibilities for security, merchandise and records, and requires retention of covered records for five years after final withdrawal under the entry. Ask CBP what separation and construction controls are needed and have the proprietor maintain required records. A pad outside the mapped boundary can still obstruct access or compromise security.

Distinguish a foreign-trade zone and document the handover

Confirm whether the facility is a Customs bonded warehouse, a foreign-trade zone (FTZ), or includes both. An FTZ is a separate program under the FTZ Board and CBP, with rules in 15 CFR Part 400 and 19 CFR Part 146. Do not assume the bonded-warehouse procedure alone authorizes a change to an activated zone; consult the zone operator, grantee, port director and counsel about the applicable approvals.

Have counsel coordinate the lease, proprietor’s obligations and developer agreement: identify each phase, permitted surveys, inventory clearance, required written approvals, security, insurance, costs and deadlines, and what happens if a phase is delayed. Sunland welcomes battery storage land inquiries from owners and authorized representatives nationwide. Share the location, approximate acreage and operating status; provide plans and sensitive records privately if requested.

Questions landowners ask

Can an empty section be handed over immediately?

Not solely because it appears empty. Reconcile the inventory and approved bonded boundary, then ask the proprietor and CBP which permission or suspension applies and when the area can be released.

Can bonded space be temporarily suspended?

The port director may suspend all or part for up to one year on the proprietor’s written application if no bonded goods are in the affected area. Confirm separation and the approved scope with CBP.

Is a foreign-trade zone the same as a bonded warehouse?

No. An FTZ has a separate statutory and regulatory framework. Determine which status applies and consult the relevant operator, grantee and CBP before changing the site.

Sources & further reading

Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.