Set out who can pursue the battery project
In the signed September 2026 Swan transaction involving solar project interests in Bates County, Missouri, section 5.14 lets Swan CE Seller LLC or its affiliates elect to develop and operate a battery project on, next to or associated with the solar project. Swan Purchaser LLC consents and agrees to cause the acquired companies to cooperate in good faith, including by granting or arranging reasonably required consents or other approvals.
For your deal, name the company that can pursue the battery and identify which purchaser-controlled companies must cooperate. Specify what they will provide, such as review of a shared access plan or a signature on a defined consent. Have counsel compare that commitment with the leases, title records, easements and utility agreements for the battery pad, access and connection. Obtain any land rights and third-party approvals the proposal still needs.

Define what needs the purchaser’s written consent
The Swan agreement requires the seller and its affiliates to avoid negative impacts on or interference with the solar project’s development, construction, operation or maintenance unless the purchaser gives prior written consent. The written-consent requirement also covers violations or defaults under specified project, financing or tax equity agreements, liens on acquired-company assets other than permitted liens, and costs or liability for acquired companies.
For example, if a proposed battery needs a road or connection used by the solar project, show how the parties would allocate access, outages, upgrade costs and repair work. Have counsel identify consent triggers and whose approval is needed for each change. Keep each signed response with the proposal it covers so a later design change can be reviewed against the same conditions.
Agree on the process for any later battery sale
The Swan agreement calls for cooperation on a potential purchase by the buyer or its affiliates of a successfully developed associated battery project. It gives the purchaser a right of first offer on a proposed sale, transfer or other disposition of that battery project. The provision leaves the price and offer procedure unspecified.
If you plan to grant a first-offer right, agree on what will trigger it, who receives notice, what documents to send, how long the purchaser has to respond and when you may seek other buyers. Check whether the development and cooperation terms carry to a successor and what happens if the original equity deal terminates. Clearway’s November 2026 filing described the Swan equity closing as conditional and expected in the second half of 2028. The reviewed filings leave battery development and any later disposition unverified.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your project or land agreement
Sunland reviews battery storage land sale, lease and existing agreement inquiries, including potential assignments, across the United States. Share the property location, your role and which project rights you want to keep or transfer. Keep signed agreements, survey exhibits and consent records for private review.
Questions landowners ask
Does purchaser consent give me the land rights I need for the battery?
Check who controls the site, access and connection rights and obtain the signed property documents and any necessary third-party consents.
When should we agree on the first-offer process?
Set the details in the sale papers before signing. Identify what triggers notice, how long the purchaser has to respond and when you can pursue another transaction.
What if the battery would add a cost for the solar project?
Identify the cost and who will bear it. Check the financing and project agreements and obtain any required written consents before committing to the change.
Sources & further reading
Sources checked November 20, 2026. The signed Swan agreement concerns a sale of company membership interests. The reviewed filings leave closing, the battery site and its underlying land rights unverified. Local rules and program details can change. Check the requirements for the actual project.