Find the device and trace its drainage
Gather the yard drainage plans, as-built drawings, maintenance records, prior permits and any UIC inventory or correspondence. Ask an engineer to locate inlets, pipes, chambers and discharge points, and show the areas that currently drain to the device. Field investigation may be needed if the records do not match the site.
Compare that information with a preliminary battery layout showing grading, equipment, access, drainage and construction work. Identify changes to the contributing area, runoff and maintenance access. An existing device may constrain the layout even if it remains in place.

Determine whether the device is a Class V well
EPA describes stormwater drainage wells as devices that infiltrate runoff below the surface. They include some dry wells and infiltration galleries. The physical design and subsurface discharge matter: a subsurface fluid distribution system or a shaft or dug hole deeper than its largest surface dimension can meet the well definition. A surface impoundment without a shaft or subsurface distribution system generally is not a Class V well.
Do not decide from the label alone. Give the drawings and findings to the UIC permitting authority and ask it to confirm how the device is classified and which federal, state, tribal and local requirements apply.
Check inventory and authorization before relying on reuse
EPA says Class V stormwater drainage wells may be authorized by rule without an individual permit when the required inventory is submitted and injection does not endanger an underground source of drinking water. The authority can require a permit, additional information or closure; state requirements may be more stringent. A submitted inventory is not by itself proof that the proposed use is authorized.
EPA’s stormwater guidance says to stop using an existing stormwater drainage well and contact the permitting authority for instructions. Ask the authority how that guidance applies to the device and its current status, including any existing inventory and authorization. Follow its direction on use, reporting and any proposed changes; do not assume continued use or a fixed approval timeline.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCompare retention, alteration and closure
Have the developer and engineer compare feasible drainage alternatives, including retaining the device, changing the system or replacing it with another solution. Show the authority the proposed drainage areas, construction and operating conditions, and ask what reviews or approvals each option requires. Stormwater design and other permits may involve separate agencies.
If closure is proposed or required, ask the UIC authority for site-specific instructions before work. EPA says Class V wells must be closed to protect underground sources of drinking water and materials managed under applicable requirements. Covering an inlet or filling a chamber without an approved approach may not accomplish proper closure.
Address the decision in the land agreement
Before signing an option or lease, ask who will investigate the device, communicate with regulators, pay for engineering and any required work, and maintain the drainage system. Have counsel review the site plan, allocation of existing conditions and what happens if reuse is unavailable or a different design is needed.
Sunland welcomes land and existing project inquiries nationwide. Share the property location, approximate acreage if known and your relationship to it, and mention the existing yard drainage device. Provide plans and agency correspondence privately if requested for review.
Questions landowners ask
Is every stormwater basin a Class V well?
No. EPA says a surface impoundment without a shaft or subsurface fluid distribution system generally is not a Class V well. The design and discharge determine the classification; ask the UIC authority to review the device.
Does an old inventory mean the battery project can reuse the well?
Not by itself. Confirm the existing status and describe the proposed drainage and changes to the UIC authority. The authority may require additional information or a permit, and other requirements may apply.
Can the project simply fill in the dry well?
Consult the UIC authority first. Proper closure must protect underground sources of drinking water and follow applicable requirements for the well and any materials removed. The replacement drainage design may need separate review.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.