Landowner guide

Can a highway agency offer right-of-way for battery storage?

A highway agency may see an apparently unused area beside a federal-aid highway as a possible battery energy storage site. Before promising a long lease or a sale, determine what property interest the agency holds and whether the proposed battery use can fit the applicable highway process and continuing transportation needs.

The short answer

Have the authorized highway grantee and its advisers identify the property interest, project limits and proposed use, then ask the state transportation department and Federal Highway Administration (FHWA) which review applies. If the project is an alternative use governed by 23 CFR 710.405, its time-limited right-of-way (ROW) agreement must address revocation, removal and agency access. A separate excess-property process applies to a proposed disposal.

Identify the land and the rights available

Obtain the acquisition documents, title and survey, approved highway ROW and project limits, federal funding records, existing easements and the grantee’s ROW manual or real estate management plan. Identify the public agency holding the relevant interest and who can negotiate. The agency may have an easement or another limited interest rather than fee title. Under section 710.405, the grantee must have sufficient legal right, title and interest to permit the proposed non-highway use.

Overlay the proposed battery equipment, foundations, fencing, cable and interconnection routes, construction staging, drainage and access on the highway plans. Show vertical and horizontal space, known utilities, maintenance routes and future highway needs. An unused-looking shoulder or adjoining tract does not establish available land or authority to lease it. A neighboring private owner should verify its own boundary and rights before offering any highway strip.

Illustration of a land parcel and surrounding landscape

Ask which federal route applies

Describe who owns and operates the battery, whom it serves, its electrical connection and the proposed rights and term. Ask the state transportation department and FHWA whether the actual installation is treated as utility accommodation under 23 CFR part 645, an alternative use under part 710, or another arrangement. Section 710.405 excludes certain railroad and public-utility uses governed elsewhere. Classification is a site-specific agency question, not a conclusion from the label “utility-scale.” Park-and-ride lots are exempt from part 710 and require their own process.

Federal utility definitions include qualifying privately owned facilities, so private ownership alone does not rule out utility treatment. Section 645.209 says the most important consideration is how the state transportation department views the installation under its own laws and regulations. FHWA’s September 2026 guidance discusses utility and alternative-use paths for electrical transmission, water transmission and broadband. It does not itself establish that a standalone battery qualifies for a transmission finding or rent exception.

Test a time-limited agreement against the project

If section 710.405 governs, a ROW use agreement may authorize time-limited occupancy by a public or private party when its conditions are met. The agreement must define its term and the design and location, protect highway safety and integrity, and establish terms for revocation and removal of improvements at no cost to FHWA. It must also address adequate insurance to hold the grantee and FHWA harmless and compliance with nondiscrimination requirements.

The agreement must require approval by the grantee and FHWA, unless assigned to the state transportation department, for significant revisions in design, construction or operation. If the state department is not the grantee and the agreement affects a federal-aid highway, its approval is also required. The rule requires access for those agencies, as applicable, for inspection, maintenance and highway reconstruction. Have the developer and its financing advisers assess whether the actual revocation, removal and access terms support the proposed investment; a private promise of uninterrupted possession cannot replace them.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Prepare the request and confirm the decisionmaker

Section 710.405 calls for a written request and supporting application to the grantee. Identify the party developing and operating the use, explain its public interest, and provide the design, maps, highway relationship, maintenance access and evidence that the project will not impair the highway or interfere with free and safe traffic. Discuss construction, inspection, emergency access and eventual removal with highway staff and qualified engineers before fixing the footprint.

Alternative-use decisions must protect continued highway operation, maintenance and safety. FHWA may assign certain approvals for non-Interstate property controlled by a state transportation department through its stewardship agreement. It may not assign to the state the decision to allow an ROW use agreement or disposal on or within approved Interstate ROW limits. These assignment provisions do not apply to grantees other than state transportation departments. Ask which agency decides the specific request and what environmental and other reviews apply. An application is not approval.

Distinguish occupancy from disposal

If the project requires ownership rather than a time-limited use, ask the grantee whether its property interest can lawfully be declared excess and conveyed. Section 710.409 provides a separate process for disposal of excess real property, with FHWA approval unless an applicable exception or stewardship assignment provides otherwise. Other public agencies may have an opportunity to acquire property with certain public-use potential. A private request does not compel an excess determination or sale.

Review the proposed transaction’s valuation and revenue treatment with the highway agency. Section 710.403 generally requires fair market value for use or disposal of interests acquired with title 23 funds, subject to listed exceptions. The September 2026 FHWA memorandum addresses exceptions for specified transmission and broadband projects; do not assume an independent battery receives a waiver or discounted rent. Environmental review and separate project permits may still apply.

Make the commercial terms fit the highway rights

Have counsel compare the proposed option, lease and any financing rights with the approved highway agreement. Specify the exact area, term, permitted work, agency access, required approvals for significant changes, insurance and who pays for removal and restoration. Address what happens if the highway agency revokes the agreement, a necessary approval is denied, or a redesigned project no longer fits. Review assignment and successor terms in the actual documents; an option or private assignment does not automatically assign an approved highway right.

Authorized property representatives nationwide can ask Sunland to review a battery storage sale, lease or existing project agreement. Share the location, approximate acreage, agency interest and known highway constraints; provide title and project records privately as appropriate. Sunland may contract and later assign its interest to a specialist developer, subject to the actual agreement and applicable highway rights. An inquiry does not establish site control, a permit or project feasibility.

Questions landowners ask

Can a private battery operator use federal-aid highway land?

Possibly. The agency must identify the correct utility or alternative-use process, sufficient property rights and applicable approvals. Private ownership alone does not decide utility classification.

Can a ROW use agreement guarantee permanent possession?

Section 710.405 addresses time-limited use and requires terms for revocation and removal at no cost to FHWA. Review the actual agreement and its commercial consequences with counsel.

Is selling highway land the same as granting an ROW use?

No. A sale requires examination of the grantee’s interest and the separate excess-property disposal process. Apparent vacancy does not establish that the land is excess or available for purchase.

Sources & further reading

Sources checked 2026-11-18. Local rules and program details can change. Check the requirements for the actual project.