Identify the land and its obligations
Map the proposed battery area, access, utility routes and any construction or laydown area against the current Exhibit “A,” airport layout plan and property records. Obtain the original federal conveyance instrument, deeds, amendments and relevant grant documents. Confirm how each affected tract was acquired; federally conveyed and federally acquired land have different procedures in the FAA manual.
Read the conveyance with airport counsel and the FAA ADO or Region. Section 22.10 says some instruments contain an automatic reversion clause that may need attention before consent to a use other than an aeronautical or airport purpose. Other obligations, including any National Emergency Use Provision, may remain during a consented use.

Describe the end user and the aviation need
Ask the developer who owns and operates the battery, who receives its electricity, whether it serves the airport or the grid, and the proposed term and physical footprint. An independent battery lease should not be assumed to be an airport purpose simply because it is on airport property. Ask the sponsor and ADO to classify the specific use under the conveyance and applicable obligations.
Compare the proposed term and footprint with current and future aeronautical demand. The FAA manual identifies the master plan, forecasts and hangar waitlists as examples of evidence. Include planned facilities, safe operations and access. Vacant land today is not proof that it will be unnecessary for aviation throughout a long lease.
Separate consent to a use from release for a sale
Section 22.10 says a sponsor proposing non-aeronautical or mixed use of federally conveyed property must request and receive FAA consent, but identifies exceptions where the use is aeronautical or an airport purpose, or is specifically permitted by the conveyance. The manual also says a consent letter is unnecessary if the instrument permits revenue production or the specific non-aeronautical use. Have the ADO review the actual documents and proposal; consent to a use is not a release of obligations.
The sponsor’s consent request includes property and acquisition documentation, present use, current and future aeronautical demand, the proposed use and its anticipated duration. FAA review considers effects on needed aeronautical facilities, compatibility, civil aviation benefit and environmental coordination. The manual states non-aeronautical lease rates must be fair market value under the revenue use policy. The sponsor and FAA determine the appropriate path and conditions for the particular request.
A sale, conveyance or exchange raises a separate release question. Section 22.13 describes a sponsor request and FAA review for releasing federally conveyed land; it calls for showing the land is no longer needed for its original purpose or present or foreseeable airport purposes. The Region or ADO must obtain written concurrence from FAA headquarters before releasing property for sale or conveyance. Do not treat consent to a lease as authorization to sell.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMake a conditional commercial decision
Before signing, have counsel address the sponsor’s authority, required FAA and other approvals, appraisal and rent, airport revenue treatment, access, aviation compatibility, construction and removal, insurance and restoration. Set milestones and explain what happens if an approval is denied, delayed or conditioned. Ask what must be returned to aviation use and when.
Sunland reviews battery storage land and existing project agreements nationwide. An authorized sponsor representative can share the airport location, approximate acreage and known conveyance issue; records can be shared privately if requested.
Questions landowners ask
Does an unused airport parcel qualify automatically?
No. Review the conveyance, present and future aviation needs, the actual proposed use and applicable FAA process.
Is FAA consent the same as releasing the land for sale?
No. The manual distinguishes consent to a land use from the release process for sale, conveyance or exchange.
Does a battery serving the grid count as an airport purpose?
Do not assume its classification. Describe the end user and operation and ask the sponsor and FAA ADO or Region to assess the specific proposal and conveyance.
Sources & further reading
FAA Airport Compliance Manual Order 5190.6C, chapter 22, sections 22.10 and 22.13, and FAA order status checked November 16, 2026. The order guides FAA personnel; the conveyance, sponsor obligations, actual project and current FAA determination control the site-specific analysis. Local rules and program details can change. Check the requirements for the actual project.