Separate the boundary from ownership
FERC describes the project boundary as the geographic extent of land the licensee must own or control for the licensed project. It can include land needed for operation, recreation, shoreline control or environmental protection. FERC also says establishing the boundary does not change the property rights an owner already holds. A boundary line alone therefore does not show who owns the fee, the scope of an easement or what a seller can grant to a battery developer.
Identify the project name, FERC project number and licensee. Request the current license, amendments and relevant orders, approved Exhibit G drawings and any applicable shoreline or other management plans. Gather a title report, recorded deeds, easements, leases, surveys and existing permissions. Ask a surveyor and counsel to reconcile the approved boundary and actual instruments with the parcel; an online map is a starting point, not a title determination.

Map the full battery proposal
Show the battery pad, equipment, access roads, utility connections, drainage and security features along with grading, trenching, staging and temporary construction access. Compare each area with the project boundary, licensed facilities, title interests and any protected, recreational or shoreline areas. Identify who controls every segment, including routes across neighboring property. A pad outside the boundary does not resolve an access route or temporary work inside it.
Give the licensee the proposed layout, methods and intended sale or lease and ask whether they are compatible with project purposes and current plans. The answer may differ for a project-related modification and a third-party non-project use. Ask what information, consultation and other federal, state or local approvals the actual proposal needs before any construction or site disturbance.
Ask which authorization applies
FERC’s compliance handbook explains that many licenses contain a standard land use article permitting a licensee to authorize certain uses or convey specified interests without prior Commission approval, subject to conditions. Other proposed uses may require a licensee application and FERC approval. The categories and conditions in the actual license matter; do not assume a battery installation qualifies merely because some roads or utility uses appear in the standard article.
Ask the licensee whether the proposed pad, access and work require its permission, a conveyance, prior FERC approval or another action, and who must prepare and submit the materials. FERC’s non-project use guidance describes the licensee filing an application where needed; FERC may approve it with or without changes or deny it. Permission for a non-project use does not itself move the project boundary. A boundary amendment is a separate question and should not be assumed available or required for every proposal.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMatch the transaction to the rights and review
A private owner can discuss a sale or lease, but the proposed agreement must respect the rights others hold and any applicable license requirements. Ask counsel to review the actual title instruments, existing agreements and any licensee or FERC authorizations. Address who obtains consents and approvals, pays for studies and survey work, manages access and restoration, and bears the risk of a changed layout, delay or denial before committing to a closing or construction schedule.
Sunland welcomes battery storage land sale, lease and existing project agreement inquiries from owners and authorized representatives nationwide. Share the location, approximate acreage and known project number or licensee; provide title, license and agreement documents privately if requested. Sunland may contract for a parcel and later assign that contract to a specialist developer. Assignment of a private contract does not itself grant hydropower project rights or approvals; review its terms and any consent requirements.
Questions landowners ask
Does a FERC project boundary mean FERC owns my land?
No. FERC says the boundary does not change existing property rights. Check the deed, easements and other actual instruments to determine ownership and the rights held by the licensee.
Can the licensee approve a battery facility without FERC?
That depends on the actual license, the rights and the proposed use. Some specified uses may be authorized by a licensee under its license; ask the licensee whether this proposal needs prior FERC approval or another action.
Will a non-project use approval remove the land from the boundary?
No. The FERC handbook says permission or a conveyance for a non-project use does not itself change the project boundary. A boundary change is a separate matter.
Sources & further reading
Sources checked 2026-11-18. Local rules and program details can change. Check the requirements for the actual project.
- FERC: Hydropower Frequently Asked Questions — Shoreline Management
- FERC: Compliance Handbook, sections 2.7.1.3 and 2.7.1.7 and Appendix B
- FERC: Guidelines for Preparing Shoreline Development Applications
- FERC: Guidance for Shoreline Management Planning at Hydropower Projects
- FERC: Managing Hydropower Project Exhibits — Drawings Guide