Landowner guide

Can a battery storage pad be built on activated foreign-trade zone land?

A proposed battery storage pad on an industrial property may overlap an activated foreign-trade zone (FTZ). Before promising a construction footprint or access route, compare the project plan with the current activated boundary and involve the zone grantee and operator.

The short answer

Obtain the current activation approval and boundary plan, then have the developer overlay the pad, fencing, roads, trenches and utility work. Ask the grantee and operator to discuss the proposed use and any boundary or security changes with the responsible U.S. Customs and Border Protection (CBP) port. A designation alone does not establish that this particular area is activated, and the right procedure depends on the actual change.

Locate the activated area first

An FTZ designation and CBP activation are different steps. Under 19 CFR 146.6, an activation application may cover all or part of the area approved by the Foreign-Trade Zones Board; the site is considered activated after the port director approves the application and accepts the executed operator bond. Do not infer the activated footprint from a parcel line, a marketing map or a zone designation alone.

Ask the grantee and operator for the current activation approval, approved site blueprint and later alteration records. Have a surveyor or project engineer compare those records with the property survey and a scaled battery layout. Include the pad, construction staging, perimeter fence, gates, access road, drainage and electrical routes. Confirm which features are inside or cross the activated boundary.

Illustration of a land parcel and surrounding landscape

Work out the change with the zone parties

Share the overlay and construction sequence with the grantee and operator. Discuss existing zone operations, merchandise movements, inventory controls, security, emergency access and who may enter through each gate. The team should ask the responsible CBP port what review the particular work requires before the layout, fence or operations change; a pad proposal does not automatically establish the answer.

Under 19 CFR 146.7(a), the operator applies in writing to the port director for approval of an alteration of an activated area, with applicable supporting documents. The regulation defines discontinuing activated status for only part of a zone site as an alteration. It defines deactivation as voluntary discontinuation of activation of an entire zone or subzone. Have the zone parties and CBP determine how the proposed boundaries and operations fit the rules. The operator must obtain its surety’s consent to a material alteration of zone boundaries even if a new bond is not required; the port director may require a new bond in specified circumstances.

Plan the transition and access

If the proposal entails deactivation, section 146.7(b) calls for a written application by the grantee, or an operator with the grantee’s concurrence, identifying the exact site on a layout or blueprint. The port director cannot approve until all merchandise in the site being deactivated that is in zone status other than domestic status has been removed at the operator’s risk and expense, and may require an accounting. Confirm the practical sequence with the operator and port instead of assuming that a lease or fence move changes activation.

Whether or not the boundary changes, coordinate construction and permanent access with zone operations. Locate gates, contractor routes, deliveries, utility entry, emergency access and maintenance rights on the plan. Identify any temporary security measures and responsibility for restoring or replacing affected fencing; the port director may review the security, suitability and fitness of an altered area.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Put the responsibilities in the deal

Gather the current boundary and approval records, survey, draft layout, applicable grantee and operator agreements, and relevant correspondence. Ask counsel to review existing occupancy, access and consent rights before granting an option, lease or sale. Clarify who requests approvals, pays for surveys and security changes, handles merchandise or operational interruptions, and bears delay if the needed arrangement is not approved.

Sunland reviews battery storage opportunities throughout the United States, including land for sale or lease and existing project agreements. An owner or authorized representative can share the location, approximate acreage and known FTZ status; detailed plans and operating records can be provided privately when requested.

Questions landowners ask

Does FTZ designation mean the whole parcel is activated?

No. Activation may cover only part of an approved zone. Check the current approval and activated boundary with the grantee and operator.

Does removing the pad area from activation mean deactivating the whole zone?

Not necessarily. The regulations call discontinuance of activated status for part of a zone site an alteration. The zone parties should confirm the appropriate procedure with CBP for the actual proposal.

Can construction access cross the activated area?

The proposed route needs review with the operator, grantee and responsible CBP port in light of the site’s operations and security. Show temporary and permanent routes on the plan before committing to them.

Sources & further reading

Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.