Start with the property and the proposed footprint
Obtain the original grant agreement, amendments, acquisition and title records, and the recipient’s real property inventory. Identify the assisted tracts, federal interest, authorized use and any other restrictions. Confirm who holds title and who has authority to negotiate; an operating facility may include parcels acquired at different times or with different funds.
Map the battery containers, setbacks, fire access, transformer, interconnection, fencing, construction laydown and permanent access against the yard or parking layout. Describe ownership, control, electricity users, operating hours and term. Compare the full footprint and construction impacts with existing and reasonably planned bus movements, maintenance, charging, parking and passenger access.

Test incidental use against transit capacity
FTA describes incidental use as a limited authorized non-transit use compatible with the approved project that does not interfere with public transportation uses. Its FAQ says an acceptable incidental use does not affect the property’s transit capacity or use. An apparently vacant corner is not enough to establish that a fenced pad and its access preserve transit capacity over the proposed term. Ask the recipient to document the operational analysis and discuss the proposed classification with the Regional Office.
Circular 5010.1F generally requires 30 days’ advance notice to the Regional Office before executing a third-party incidental-use agreement that encumbers title, exceeds one year or permits third-party real property fixtures, with an exception for utility, ingress and egress uses. The notice includes the entire draft agreement and exhibits. The circular says the recipient need not receive FTA concurrence before proceeding, but FTA’s failure to protest does not itself establish concurrence that a use qualifies. The circular also advises that incidental-use agreements be revocable; discuss whether the developer’s proposed tenure and financing can accommodate revocation to protect transit use.
Consider joint development or disposition separately
FTA distinguishes incidental use from joint development, which is a capital project. Joint development on FTA-assisted property must satisfy statutory criteria, including economic benefit or private investment; either enhanced transit effectiveness together with a physical or functional relationship to transit, or new or enhanced coordination between public transportation and other transportation; a fair share of revenue for public transportation; and applicable fair-share costs. A privately financed battery or lease revenue alone does not establish eligibility. FTA asks sponsors to submit a joint development project request to the Regional Office; planning, environmental and other requirements may apply.
The recipient must retain satisfactory continuing control and the ability to carry out the original purpose. An approved joint development arrangement can convey an interest while the property remains subject to the federal grant. Disposition is a separate process for property no longer needed for its originally authorized purpose and settles the federal interest. Do not assume that a lease, sale or settlement is authorized merely because a pad is proposed; ask the recipient and FTA which process and conditions apply.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMake any commercial commitment conditional
Before signing, have transit counsel address authority, FTA review and any other approvals, term, rent and revenue treatment, construction, emergency access, insurance, removal and restoration. Include milestones and consequences if an approval is denied, delayed or conditioned, and protect the transit operations and access the recipient must maintain.
Sunland reviews battery storage land opportunities nationwide. An authorized recipient representative can share the site location, approximate acreage and known grant or transit-use issue; supporting records can be shared privately if requested.
Questions landowners ask
Does unused space at an operating transit facility automatically qualify for a battery pad?
No. Review the complete footprint and its effect on transit capacity and use, the grant obligations and the proposed term with the recipient and FTA.
Is a battery lease automatically joint development?
No. Joint development is a capital project subject to statutory eligibility criteria and FTA review. The project’s relationship to transit must be evaluated.
Does 30 days without an FTA objection approve incidental use?
No. Circular 5010.1F says failure to protest does not itself establish concurrence that the use qualifies.
Sources & further reading
FTA Joint Development FAQ, Circular 7050.1C, the January 2025 joint development request form update, and Award Management Circular 5010.1F checked November 16, 2026. The grant, property history and FTA Regional Office determination control the site-specific process. Local rules and program details can change. Check the requirements for the actual project.