Trace the track and the proposed project
Use a current survey and site visit to map the rails, connection and switches, crossings, rail corridor, adjacent properties and access routes. Overlay the battery enclosure and foundations, transformers, cables, stormwater facilities, fire access, construction staging and delivery paths. Follow the track beyond the proposed pad to determine whom it served and where it connects; a short segment visible on one parcel may be part of a longer facility.
Identify the current and former freight customers, property owners and serving carrier. Ask whether any service, operating rights or access are retained and whether other customers or utilities depend on the corridor. Record what is known and unknown rather than treating a rusty track, paved crossing or long period without trains as proof of legal abandonment.

Determine rail status and any federal proceeding
Under 49 U.S.C. 10903, a rail carrier subject to STB jurisdiction that intends to abandon part of its railroad lines or discontinue all rail transportation over part of its lines must apply to the Board, and the action may occur only as authorized under the chapter. Other authorized procedures, including exemptions, may apply. An STB authorization, its effective date, conditions and whether abandonment was consummated are questions for the specific record; a proposed abandonment is not the same as a completed one.
Section 10906 says the Board does not have authority under that licensing chapter over construction, acquisition, operation, abandonment or discontinuance of spur, industrial, team, switching or side tracks. Whether these tracks actually fit that category is a fact-specific legal question, not a conclusion established by calling them a spur. Private track can raise a different classification question. The exception does not decide property or contract rights and does not mean all other legal requirements disappear. The STB describes its jurisdiction and preemption as fact-specific.
Collect the agreements and verify property rights
Obtain the recorded deeds, title commitment and exceptions, surveys, easements, licenses, crossing agreements and any sidetrack or industrial track agreement and amendments. Ask for carrier correspondence, service and termination records, asset ownership and maintenance records, and any STB docket, decision, exemption, conditions or notice of consummation that might apply. Search STB records using current and predecessor carrier names, location and relevant docket numbers; an unsuccessful search alone does not prove no rights remain.
Have rail and local real-estate counsel compare the documents with the surveyed route. Determine who owns the underlying land, rails and related equipment, and who may use, access or maintain them. An easement, lease, contract or other interest may affect development even where no Chapter 109 abandonment authorization is needed; conversely, a deed or a private agreement alone does not establish federal rail status. Seek written confirmation from the carrier and other identified rights holders about the proposed change and the steps needed to resolve their interests.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMake site control match what can be delivered
Before granting an option, lease or sale, have counsel define the area and rights the owner can actually convey. Identify any retained rail corridor, access and crossings and evaluate a revised battery layout that avoids unresolved rights. Make the developer’s design, access, investigation rights and schedule consistent with the actual property and operating arrangements.
If the plan depends on clearing a conflicting rail interest, address responsibility and cost for obtaining written releases or other necessary agreements, title endorsements and applicable authorizations, as well as deadlines and what happens if a party refuses or a decision is delayed. Avoid an unconditional promise of exclusive possession or a fixed construction date before those matters are resolved. Coordinate environmental due diligence, interconnection, local permitting and emergency access separately.
Prepare the first conversation
Provide the developer and advisers a survey showing the track, photographs, proposed footprint, known carrier and the relevant title and agreement documents. Ask the carrier and counsel to identify outstanding rights, operational needs and the appropriate process for the proposed use. Preserve records of responses and any conditions in the transaction file.
Sunland welcomes battery storage land and existing project inquiries nationwide. Share the approximate acreage, location, industrial history and known rail status; provide title and commercial records privately when needed.
Questions landowners ask
Does a disused track automatically leave the site free for a battery pad?
No. Track status, federal proceedings and property and contractual rights require investigation. Ask the carrier and qualified counsel before promising possession.
Does every industrial spur need an STB abandonment application?
No. Section 10906 excludes specified spur and other tracks from the Board’s authority under the licensing chapter. Confirm the actual classification and any other applicable rights or requirements.
Does an STB abandonment decision give the landowner clear title?
Not by itself. Review the complete proceeding and its status, and separately examine deeds, easements, contracts and any remaining rights with counsel.
Sources & further reading
Federal statutes and STB guidance checked November 16, 2026 Pacific. Classification, authorizations and property rights depend on the particular track and records. Local rules and program details can change. Check the requirements for the actual project.