Collect the records before agreeing on the footprint
Request the latest Tier II submissions and supporting inventory, safety data sheets, chemical locations, emergency contacts and any correspondence with state and local authorities. Ask the current operator which records are current, what has changed and whether any locations or details are confidential. An old report describes a reporting period; it is not proof of the current inventory.
Place the proposed battery footprint, access routes, retained industrial operations and chemical storage areas on one plan. Identify where the parties need shared access, emergency response access or room to remove material. Ask the operator to confirm the actual locations and expected removal or continued use.

Identify control during each phase
Make a handoff schedule for signing, construction, any overlap with the industrial tenant, possession and operation. For each phase, identify the parties operating the relevant facility, their areas of control and contacts for emergency responders. A parcel line alone does not settle the regulatory facility boundary or responsibility.
Ask the existing operator, developer and their advisers how facility boundaries and owner or operator status apply to the actual arrangement. A landlord is not automatically responsible for a future report merely because it owns the land, and an old operator’s filing does not automatically become the new operator’s filing.
Assess the chemicals and thresholds
EPCRA chemical inventory reporting applies to covered facilities and chemicals under the applicable rules, including safety data sheet requirements, quantities and thresholds. EPA says a hazardous chemical at or above its applicable reporting threshold at any one time can trigger Sections 311 and 312 requirements. Extremely hazardous substances can have lower thresholds; state requirements may differ.
Ask each potential operator to evaluate actual chemicals, quantities and timing, including construction and overlap, against applicable federal and state rules. Do not infer a filing simply from the term battery storage or assume that an industrial report covers the proposed project. Check the state’s reporting procedures and consult the responsible authorities about facility-specific questions.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut the handoff and emergency access in the agreement
Have counsel review who supplies and updates records, removes or retains materials, controls access, coordinates responders and handles reporting during overlap and after possession changes. Agree on a process for changed inventories or plans, and identify who bears investigation and removal costs. Contract allocation does not itself decide statutory responsibility.
For covered facilities, EPA describes annual inventory reporting for the previous calendar year by March 1 to the relevant emergency response commission, local emergency planning committee and fire department. Confirm the recipients, format and deadlines applicable to the facility with the state program. Sunland welcomes property and existing project inquiries nationwide for sale or lease; share the location, approximate acreage and your relationship to the site, and provide sensitive records privately if requested.
Questions landowners ask
Does an old Tier II report establish the current chemical inventory?
No. It describes a prior reporting period. Ask the operator to reconcile it with current chemicals, quantities and locations and with the planned transition.
Does a battery site automatically need a Tier II report?
The answer depends on the applicable rules, facility, chemicals and quantities. The prospective operator should evaluate its actual operations and state requirements.
Can the lease assign every reporting duty to the tenant?
The parties can allocate tasks and costs in the agreement, but statutory responsibility depends on the facts and applicable law. Obtain advice about the facility and each phase.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.