Landowner guide

Can an MTSA-regulated waterfront facility sell or lease land for battery storage?

An owner of an operating waterfront facility may want to sell or lease a portion of its land for a battery energy storage system. When the facility is already subject to Maritime Transportation Security Act (MTSA) rules, the proposed property line is only one boundary to review. The existing facility security arrangement, construction access and continuing maritime operation also shape the transaction.

The short answer

Begin with the facility security officer (FSO), the facility owner or operator and the cognizant Coast Guard Captain of the Port (COTP). Determine how the proposed footprint and access relate to the regulated facility and its approved security arrangement, and what review or amendment is needed before changes take effect. A deed, lease or tax parcel map alone does not establish that the battery area is outside the regulated facility.

Start with the existing facility and proposed footprint

This discussion concerns land at an already regulated waterfront facility, not an assumption that all waterfront property is regulated. The applicability provisions in 33 CFR 105.105 depend on facility activities and other criteria. Confirm the regulated facility, its owner or operator, the responsible FSO and cognizant COTP, and whether the facility uses an approved Facility Security Plan (FSP) or an applicable alternative security program. Have the responsible parties determine how the existing security boundary relates to the land being offered.

Prepare a scaled proposal for authorized review showing the prospective sale or lease area, battery equipment, access and utility routes, grading, staging, construction workspace and restoration. Identify what the maritime operation needs to retain, including operating access and emergency response routes. The parcel, project footprint, physical fence and security boundary may not coincide. A small battery pad can still require access or utility rights across an operating facility.

Illustration of a land parcel and surrounding landscape

Protect the security plan and review the boundary

The FSP is sensitive security information under 33 CFR 105.400(c), protected under 49 CFR part 1520. Do not upload the plan or security diagrams to a general inquiry form or circulate them with a marketing package. The FSO should control access and arrange review only by authorized people using appropriate protected channels. For an initial land inquiry, provide a non-sensitive summary of the proposed transaction and refer detailed security questions to the FSO.

Ask the FSO and COTP to review the proposed configuration: would the battery area remain within the facility security arrangement, or is a change to the facility boundary proposed? What changes, if any, are needed to the approved plan or applicable program? How would a modified gate, fence, shared road or emergency access affect the retained waterfront operation? Obtain their direction before treating a boundary or access design as settled. Moving a fence, recording a deed or signing a lease does not itself establish regulatory approval.

Sequence review, construction and ongoing access

Discuss both the permanent project and each construction phase with the FSO. Temporary staging, deliveries, utility crossings and construction traffic can affect the operating facility even if the final battery area is separate. Identify who will coordinate with the COTP, what submissions or approvals are needed, and what temporary arrangements must be accepted before work begins. Plan realistic time for review and for changes to the project if the original configuration does not work.

Identify which workers need access to secure areas, when and for what tasks. Section 105.255 requires, among other measures, that a project worker seeking unescorted entry to a designated secure area generally have a duly issued Transportation Worker Identification Credential (TWIC) and authorization; ask the FSO about applicable exceptions. A TWIC alone does not grant site access. The facility also must have procedures for identity and escort of people without a TWIC; ask the FSO what the approved procedures and operator’s arrangements allow. Do not assume every construction worker needs a TWIC or that an escort will automatically be available.

Address operating access after construction as well: maintenance visits, replacement equipment, utility work and emergency response may require different schedules and permissions. Confirm usable routes and responsibilities with the facility and relevant responders, subject to the approved security arrangements. Do not promise unrestricted access in the real estate documents before the parties know how access will be administered.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Check amendments, audits and timing

Under 33 CFR 105.415, an owner- or operator-initiated FSP amendment generally must be submitted to the cognizant COTP at least 30 days before it is to take effect, unless the COTP permits a shorter period. The COTP can also initiate an amendment; that process has its own notice and timing provisions. A proposed amendment requires Coast Guard review and approval. Coordinate the submission and schedule with the FSO and COTP rather than treating the 30 days as automatic approval.

Section 105.415 also requires an FSP audit when facility ownership or the operator changes, or when the facility is modified, including physical structure, emergency response procedures, security measures or operations. The FSO must amend the FSP with the new facility owner’s or operator’s name and contact information and submit the affected portion for review and approval when there is such a change. If an audit requires amendment of the assessment or plan, the rule has a separate submission deadline. A land sale, lease or assignment does not by itself establish that the regulated facility has a new owner or operator; determine the actual roles and effects with the responsible parties.

Build a practical transaction record

For the initial discussion, assemble a non-sensitive packet: approximate location and acreage, current ownership, whether a sale, lease or existing agreement is proposed, a general description of the operating waterfront use, proposed project timetable, and contact information for the person authorized to coordinate with the FSO. Keep protected security documents and detailed security drawings out of general intake. The FSO can arrange a separate authorized review of information needed to assess the site.

For due diligence, counsel and the project parties should also review the survey and title, existing leases and easements, lender or landlord consents, utility and access rights, and other restrictions through appropriate channels. Ask who owns and operates the retained facility and proposed battery site, who controls the relevant land and access, and whether the proposed sale or lease affects existing obligations. Local land use, environmental, fire and electrical approvals may be separate from maritime security review.

Make the agreement match the review

Have counsel address the review period, conditions to closing or commencement, responsibility for submissions and costs, access and escort arrangements, construction sequencing, insurance, restoration, maintenance and emergency coordination. Provide a process for changes requested during agency or facility review and a clear outcome if the needed arrangement cannot be obtained. Private contract rights and an assignment are separate from any required government review or approval.

Sunland welcomes land sale, lease and existing agreement inquiries nationwide. Share the non-sensitive basics of the waterfront property and proposed battery opportunity. Sunland may contract for a parcel and then assign its interest to a specialist; discuss assignment terms and any necessary consents before signing. Detailed facility security information belongs in an authorized review channel, not the general inquiry.

Questions landowners ask

Does a new parcel line remove the battery site from MTSA requirements?

Not by itself. Ask the FSO and cognizant COTP how the proposed area relates to the regulated facility and what review or changes are needed.

Must every battery contractor have a TWIC?

No blanket conclusion follows from the project alone. Requirements depend on the area and access needed. Project workers seeking unescorted access to a designated secure area generally need a duly issued TWIC and authorization; discuss applicable exceptions and permitted escort arrangements with the FSO.

Does a sale or lease always change the facility operator?

No. Determine who will actually own and operate the regulated facility. A change in facility owner or operator has specific plan amendment and audit requirements, while other modifications can also require an audit.

Can I send the security plan with my inquiry?

Do not upload the FSP or security diagrams to general intake. The FSP is sensitive security information; have the FSO arrange any authorized review through an appropriate protected channel.

Sources & further reading

Sources checked 2026-11-18. Local rules and program details can change. Check the requirements for the actual project.