Compare the property records and proposed layout
Gather a current survey if available, deed, title materials and any recorded easements or agreements concerning the levee and access. Ask the developer to show the proposed battery pad, equipment, roads, buried lines, staging areas and construction access on a property plan. Include temporary as well as permanent use.
Ask the non-federal sponsor, if there is one, and USACE district how to obtain or identify the lands and real property interests acquired for the federal project, and compare those records with the survey and concept plan. A visible levee or a line on an online map does not establish the limits of those rights. Ask a surveyor or attorney to help reconcile uncertain boundaries or documents.

Ask about Section 408 and other permissions
If the levee name is unknown, search the USACE National Levee Database for a candidate system and share its name or system ID with the district to help identify the project and any non-federal sponsor. Verify the actual project property interests with the district and sponsor; the database alone does not establish them. Contact the USACE district’s Section 408 coordinator and the non-federal sponsor, if there is one, early. Share the property location and concept plan, and ask whether the proposed use or work requires Section 408 review, what information the agencies need, and how a request should be submitted. The national USACE Section 408 page provides a district coordinator finder.
USACE describes Section 408 as its process for considering permission for alterations to its civil works projects. Its Sacramento District says permission is required for proposed alterations within lands and real property interests acquired for a USACE project and directs requesters to the sponsor. The responsible district should address the actual proposal. Being nearby alone does not establish the answer, and there is no universal setback to apply from this guide.
Ask the sponsor and district about any separate property rights, local approvals or other permits that may be needed. A Section 408 decision and a landowner’s agreement do not automatically supply every other authorization.
Address uncertainty in the agreement
Ask the developer who will obtain the project records and agency decisions, prepare any required request, pay associated costs, and revise the layout if needed. Discuss the proposed access and construction rights with your attorney, including timing, restoration and what happens if a necessary permission is denied or conditioned.
A flood map addresses a different question from the extent of a federal project’s property interests and Section 408 review. State waterway requirements may also apply separately. Ask the relevant authorities about each issue instead of treating a flood-map result or a state permit as a Section 408 determination.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPrepare an inquiry
Sunland welcomes nationwide land and existing project inquiries. Share the property location, your relationship to it, approximate acreage if known, and the levee or agency name if available. Provide surveys, easements and concept plans privately if requested for review.
Questions landowners ask
Does land near a federal levee always need Section 408 permission?
Proximity alone does not answer the question. Ask the non-federal sponsor, if there is one, and USACE district Section 408 coordinator to review the proposed work and project property interests.
Does a flood map show all federal levee property rights?
Do not rely on it for that purpose. Ask the non-federal sponsor, if there is one, and USACE district about project lands and property interests, and compare the records with your survey and proposed layout.
Does the landowner’s agreement replace agency permission?
No. Ask the responsible agencies which reviews and permissions apply to the specific proposal, and have your attorney review the land agreement.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.