Find the easement and identify the operator
Collect the recorded easement, amendments, maps and exhibits, a recent survey if available, and any correspondence or existing crossing agreement. Ask a title professional or attorney to help locate missing documents and identify the rights and restrictions that apply to the property. PHMSA notes that pipeline easements typically describe operator and landowner rights and may address the right-of-way width and operator access.
Find the current pipeline operator using the agreement, correspondence or marker information, and confirm the correct contact. A marker can help identify a pipeline, but do not use it alone to establish the pipe’s exact location, depth or easement boundaries.

Show the operator what must cross
Ask the battery developer for a preliminary plan showing the route, the proposed crossing of the right-of-way, road construction or improvements, grading, drainage, staging and underground work. Request the expected vehicle types, loads, frequency and construction schedule. Mark what is unknown; a concept drawing is not a surveyed alignment or engineering approval.
Provide the operator the plan and ask for a written response identifying its review process, required information, crossing conditions and any inspection or agreement it requires. PHMSA advises owners and developers to consult the operator early and consider easement constraints and construction activities. Do not assume the easement automatically allows or forbids this particular crossing.
Compare an alternative before promising access
Ask the developer to investigate an alternative route or site layout if the proposed crossing cannot be confirmed, needs changes or would create unacceptable cost or delay. Compare the routes for land control, road work, delivery requirements and operator access. An alternative may need other owners’ permissions or separate reviews; a line on a map does not secure those rights.
Ask who will prepare the engineering, contact the operator, pay for review and any agreed protection measures, and maintain the crossing. Have your attorney review the easement and proposed access terms, including responsibility if the route changes or the operator needs access for inspection or repairs.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCoordinate before ground disturbance
Ask the developer and contractors to contact 811 before excavation and follow the applicable local process and operator instructions. Locating utilities and operator review are separate steps; neither a map nor an 811 request substitutes for a crossing review or engineering.
Sunland welcomes nationwide inquiries about land and existing project opportunities. Share the location, your relationship to the property, approximate acreage if known, and whether a pipeline right-of-way intersects the proposed access. Send easement documents privately if requested for review.
Questions landowners ask
Does a pipeline easement prevent a construction crossing?
The answer depends on the easement, the proposed work and the operator’s review. Gather the documents and ask the operator about the specific crossing.
Can a pipeline marker establish the crossing location?
A marker can help identify the pipeline and operator, but it does not establish the exact pipe location or easement boundary. Ask the operator and qualified professionals to help verify the route.
What if the crossing is not workable?
Ask the developer to evaluate a different route or site layout and identify any additional land rights, reviews, costs and timing involved.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.