Find the authorization and the obligations that remain
Collect the signed Department of the Army permit or nationwide permit verification, approved plans, special and regional conditions, modifications, correspondence, completion reports and any mitigation, monitoring or maintenance records. Use the permit number and issuing district to request missing documents. Identify the permittee, the authorized activity, location, dates, any outstanding requirements and whether authorized structures or work still exist. An expired construction period does not by itself answer whether conditions continue to apply.
For example, a dock or bulkhead may remain on the waterfront the industrial owner plans to retain, while a filled area, access route or required mitigation lies on the tract offered to a battery buyer. Compare the permit drawings and mitigation area with a current survey, title documents and the proposed sale or lease boundary. Include easements, access, drainage and areas needed for inspection, maintenance and monitoring. Ask a surveyor and environmental counsel to resolve discrepancies.

Understand the sale-transfer paperwork
The standard Department of the Army permit form in 33 CFR part 325, appendix A says that if the permittee sells the property associated with the permit, the permittee must obtain the new owner’s signature in the space provided and forward a copy of the permit to the issuing office to validate the transfer. The form also states that when authorized structures or work still exist at transfer, its terms and conditions continue to bind the new owners. Read the actual issued permit and ask the district how its requirements apply.
For a nationwide permit verification, the 2026 nationwide permit general condition 29 provides that a permittee selling the associated property may transfer the verification to the new owner by submitting a letter to the appropriate Corps district. Attach a copy of the verification; the letter must include the prescribed statement and the transferee’s signature and date. The statement addresses continuing conditions and liabilities. The 2026 nationwide permits took effect March 15, 2026. Confirm the applicable permit version, regional and case-specific conditions and the district’s instructions before relying on this process.
Ask the district about a partial sale or lease
A battery buyer might acquire an upland portion while the seller retains the permitted dock, or a developer might lease only the battery footprint. The standard sale language does not establish an automatic transfer route for every partial conveyance or lease. Give the issuing district the permit number, existing and proposed boundaries, retained structures, mitigation areas and a description of each party’s rights. Ask in writing whether and how the authorization should be transferred, modified or otherwise addressed and which obligations remain with each party.
Do not assume a private contract alone changes obligations under the permit or releases the original permittee. Have counsel address allocation of costs, access, inspections, maintenance, monitoring, corrective work and agency communications, including what happens if the district requires a different arrangement. Obtain necessary agency responses and other consents before closing or granting access, as appropriate.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landReview new battery work separately
A transfer concerns an existing authorization and its conditions. It does not authorize a new battery facility, road, utility crossing, grading, drainage change or additional fill. Provide the district and project specialists with a complete layout and construction methods, including temporary work and offsite connections, and ask whether separate Corps authorization, modification or other review is needed before work begins. State, local and other approvals may also apply.
Sunland welcomes land sale, lease and existing agreement inquiries from owners and authorized representatives nationwide. Share the parcel location, approximate acreage, proposed transaction and what you know about the existing permit. Sunland may contract for a parcel and then assign its agreement to a specialist developer; assigning a contract does not itself transfer a Corps permit. If the property is already under contract or subject to an assignment, a specialist can discuss the existing agreement; provide documents privately if requested.
Questions landowners ask
Does selling the land automatically authorize the battery project?
No. An existing authorization covers its specified activity and conditions. Ask the Corps district whether the new battery work requires a separate authorization or other review.
Can the seller keep a permitted dock while selling the upland?
That depends on the permit, the boundaries and continuing obligations. Map the retained dock, permitted work and mitigation, and ask the issuing district how to address the partial sale.
Does a battery lease transfer a nationwide permit verification?
Do not assume it does. General condition 29 describes a sale of associated property to a new owner. Ask the issuing district how the particular lease and continuing obligations should be handled.
Sources & further reading
Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.