Identify the borrower, land and existing security
Start with the entity on the deed and the actual loan relationship. An electric cooperative may be a Rural Utilities Service (RUS) borrower, but a USDA connection alone does not establish which program or security documents apply. Gather the deed, current title commitment, survey, loan contract, RUS mortgage or deed of trust, supplements, amendments and all other financing and security agreements. Have counsel identify the current mortgagees, successors and any trustee, as well as the property and interests covered. RUS Bulletin 1717M-2 explains that electric borrower capital assets are ordinarily pledged and that supplemental lenders may share the security.
The parcel may contain retired equipment alongside active lines, underground cable, drainage, access or protective buffers. Engineering and operations staff should map what remains in service, required clearances, future maintenance and emergency access. The proposed battery pad, fencing, roads and cable routes must fit around those needs. A vacant-looking yard does not establish that all utility rights can be conveyed or that a battery can connect to neighboring facilities.

First decide whether the disposition needs RUS approval
Section 1717.616(b) permits a disposition without prior RUS approval only when its conditions are satisfied together. Among them, the borrower must not be in default to RUS; must meet the specified coverage ratios or other applicable security-document financial requirements in the most recent year with available data; and the disposition must not reduce existing or future requirements under a government-pledged wholesale power contract. Fair market value must be obtained and no employee or board member may have a direct personal financial interest in the disposition.
The aggregate value of assets disposed of in any 12-month period must be less than 10 percent of net utility plant before the disposition and not exceed $10 million. The rule also specifies a retained-interest condition: the borrower does not retain an interest, or the transaction is a qualifying capital lease under the referenced accounting rule in which the borrower retains no right to use the asset during the lease term, with proceeds handled as specified. Do not presume that an ordinary long-term ground lease qualifies merely because its rent is modest. Counsel and the borrower’s RUS representative should assess the precise rights, valuation and current borrower circumstances.
All dispositions also have requirements under subsection (c), including fair market value, creditors’ interests, required legal and organizational approvals before delivery, and a satisfactory remaining operating unit without jeopardizing repayment or impairing loan collateral, subject to the rule’s stated circumstances. If the transaction falls outside subsection (b), obtain the required RUS approval; a jointly held lien calls for joint approval under subsection (d). The board, management, counsel and lenders should establish who makes each decision and retain the evidence supporting it.
Then resolve the lien on the particular interest
Permission for a transaction and removal of a lien answer different questions. If a disposition needs no prior RUS approval but the purchaser requires the government’s lien released, section 1717.616(d)(2) calls for a transmittal letter requesting a partial release or RUS Form 369. Borrower or purchaser counsel should prepare the proposed release; the borrower is responsible for its accuracy and legal effectiveness and should obtain another creditor’s execution and acknowledgment where needed. Submit the transaction and proposed instrument early enough for review, execution and recording.
A title company and counsel should determine what a buyer or proposed leasehold lender actually requires. A lease may call for consent, an agreement governing priority, or other treatment of the leased interest; do not assume a fee release is either necessary or sufficient. Identify every party whose lien or consent affects the deal, including RUS, supplemental mortgagees and any trustee. An approval letter, form, or a single lender’s signature should not be treated as proof that all necessary interests have been released.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDraw the release and protect the retained system
For a partial parcel, commission a survey and legal description that matches the deed or interest conveyed and the proposed release. Show the parent tract, exact area to be released, retained facilities, easements, access and proposed construction corridors on coordinated exhibits. Counsel should check the underlying and current mortgages, deeds of trust, supplements and applicable recording information, including after-acquired-property provisions. Bulletin section 8 and its sample exhibits are starting points for counsel, not substitutes for a property-specific instrument.
Define the rights the cooperative must retain for inspection, repair, replacement, emergency response and future system work, including access across the transferred area where needed. Check whether existing easements already provide them and whether new, recordable reservations or easements must be negotiated. Coordinate fence lines, gates, drainage, excavation and construction sequencing with the battery project and the utility’s safety personnel. A release of one described area should not accidentally affect security on the remaining property.
Plan the application and proceeds before closing
Assign a borrower representative to coordinate with RUS and supplemental lenders. For a required disposition approval, assemble Form 369 and supporting information requested under section 1717.616(f) and Bulletin section 6, including the transaction documents, property and buyer details, consideration, valuation, customer and system impacts, and financial information as applicable. For a release request under subsection (d)(2), the rule lists the information for a transmittal letter, including property and purchaser details, book value, consideration, fair market value, proposed handling of net proceeds, distributions to employees or board members, and customer effects. Confirm the current submission package with RUS.
Account for proceeds even if prior disposition approval is unnecessary. For gross proceeds below $50,000, subsection (e) directs deposit into the general fund for utility-business purposes. For individual property dispositions with gross proceeds of $50,000 or more, the rule describes alternatives including deposit into the Construction Fund Trustee Account for utility system construction or acquisition, with written notice to RUS, or specified debt prepayments. The rule contains special cases and discretionary exceptions; a general-fund exception based on no balance in reserve and no anticipated new RUS loan application requires written RUS approval. Have finance staff and lenders confirm the applicable treatment, accounting and closing instructions before promising unrestricted use of sale or lease proceeds.
Structure a workable battery storage proposal
Compare an outright sale of the identified parcel with a lease, including extensions, purchase options, assignment, financing rights and restoration. Counsel can make closing or delivery conditional on the specific approvals, release or other lien treatment, acceptable title and survey, and the project’s diligence. If an agreement is already signed, review its deadlines, access rights and amendment or termination provisions now; a signature does not obtain lender or agency approval. Build time for board action, RUS and co-mortgagee review, survey and recordation into the schedule.
Sunland considers open land and BESS opportunities nationwide and may contract for a property and assign the opportunity to a specialist. Provide the location, acreage, intended sale or lease, retained utility uses and known borrower and mortgage status for an initial discussion. Interconnection studies, site design, permitting and independent legal and lender review remain necessary, and neither an inquiry nor an agreement automatically secures RUS approval or a lien release.
Questions landowners ask
Does RUS permission to sell release the mortgage lien?
No. Permission to dispose of an interest and an effective partial release are separate matters. Identify each secured party and obtain and record the required release or other lien treatment.
Is a ground lease outside the RUS disposition rule?
No. The definition includes leases and other transfers of an interest in a capital asset. Whether a particular lease meets every condition for proceeding without prior approval requires review of its terms and the borrower’s circumstances.
Can the cooperative keep all sale proceeds for general purposes?
The rule prescribes treatment based on the disposition and proceeds, with specific exceptions and discretionary approvals. Finance staff should confirm the applicable account or prepayment instructions with RUS and secured lenders.
Does a neighboring substation mean the battery can connect?
No. Available capacity, upgrades, costs and timing require the applicable interconnection process and studies.
Sources & further reading
Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.