Find the agreement and the actual performance period
An EPA RLF cooperative agreement funds an intermediary, often a local government or development agency, which in turn makes cleanup loans or subgrants. The EPA award to the intermediary, the site-specific subgrant or loan, and any cleanup contract are different documents. Identify the deed owner, subgrantee or borrower, RLF administrator and the EPA project officer. Collect the signed site agreement and amendments, EPA cooperative agreement and relevant terms, approved cleanup plan, schedule, property description, title report and recorded restrictions.
For a subgrant, establish its actual award date and period of performance, including any extensions or amendments. EPA’s June 2025 FAQ describes ownership at award and throughout that period. Physical cleanup completion, a certificate of occupancy or a planned end date is not necessarily the end of the agreement. Get written confirmation from the administrator, with EPA involvement as needed, before treating a transfer date as available. Continuing land-use or monitoring obligations can survive that period.

Test a proposed sale or ground lease
Map the proposed pad, access and utility corridors against the funded site and deed boundaries. Selling even part of the site during subgrant performance raises an ownership question; ask the administrator and EPA to evaluate the exact parcel and transaction before signing a binding conveyance. Do not assume that an option, delayed closing or splitting a parcel resolves the issue. Counsel can coordinate a conditional agreement, timing and any required written approvals.
With a ground lease, the existing owner generally retains title, but a lease is not automatic clearance. Provide the draft term, renewal and purchase options, easements, construction and excavation rights, assignment and financing provisions to the administrator and cleanup regulator. Confirm that the proposed interest and site control satisfy the award and do not interfere with cleanup, inspections, institutional controls or access. A lease or easement may also require consent under recorded restrictions or other contracts.
Separate the subgrant from a loan
EPA’s FAQ distinguishes a subgrant from an ordinary RLF loan: site ownership is required for the subgrant at award and throughout its performance, while ownership is not a federal loan prerequisite in that comparison. Eligible public and nonprofit entities may qualify for subgrants; a private for-profit firm or individual may be eligible for an ordinary loan but not a subgrant. Site and applicant eligibility, liability and local program conditions still matter. Ask the administrator about the actual instrument rather than assuming a developer can take over the existing award.
A loan must be repaid and can be secured by a mortgage, deed of trust or other collateral. Review the note, security documents, due-on-sale and leasing clauses, assignment rules and guarantees. Ask the lender for a written payoff, consent, partial release or subordination process where applicable. A lease may affect collateral even when title stays with the owner. A discounted loan has its own eligibility and award conditions; do not assume it is interchangeable with a subgrant or available to a for-profit borrower.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMatch the cleanup and construction schedules
Ask the qualified environmental professional and regulator for the current cleanup decision, analysis of alternatives, completion and monitoring records, contamination maps, engineering controls and institutional controls. Overlay battery foundations, grading, cable trenches, stormwater work and emergency access. Determine whether work would disturb a cap or containment system, require a revised cleanup plan, permits or regulator approval, or change a remedy designed for a different use.
Build a schedule from remaining cleanup milestones through verified agreement end, any required releases and BESS diligence, permits, interconnection and construction. Set access, notice, insurance and responsibility for unexpected contamination, repair of controls and long-term monitoring in the transaction documents. Allocate costs for studies, design changes and delays; retain a workable exit if a necessary approval or safe design is unavailable.
Apply the terms of this award
Ask the administrator which EPA cooperative agreement and amendments, site-specific subgrant or loan, and any post-closeout agreement govern the money being used. EPA’s June 2025 FAQs generally assume FY22 or later terms, sometimes FY23 or later, and explain that terms vary. For example, subgrant caps depend on the applicable terms and funding sources; do not apply a current figure retroactively to an older award. EPA’s current RLF page provides FY27 application guidance for new applicants, which does not replace the signed terms of an existing award.
Confirm allowable cleanup costs, procurement and labor requirements, reporting, any cost share, and restrictions on combining funds with the administrator. An RLF is cleanup financing, not a promise to fund battery equipment or development costs. Keep costs and funding sources distinct and do not charge the same expense twice. Counsel and the administrator should resolve how any proposed transaction affects the actual award.
Prepare an initial BESS inquiry
An owner or authorized representative can provide the location, approximate acreage, ownership, existing uses, access, nearby electrical infrastructure, preferred sale or lease and known cleanup status. Identify the RLF administrator and whether funding is a subgrant or loan. Share sensitive title, financing and environmental records privately during diligence.
Sunland considers battery storage land opportunities nationwide and may contract for land or assign an opportunity to a specialist. A discussion can test site and transaction fit; project feasibility, funding and approvals are not guaranteed. Consult environmental and real estate counsel and the relevant agencies about the specific property.
Questions landowners ask
Can the owner sell before cleanup work ends?
A subgrantee must own the site at award and throughout the subgrant agreement’s period of performance. Ask the administrator and EPA to evaluate the exact proposed transfer and confirm the actual period before committing.
Does a ground lease automatically comply?
No. Retaining title is relevant, but the lease rights and construction must also fit the award, cleanup requirements and recorded restrictions. Obtain required approvals.
Can a private developer receive an RLF subgrant?
EPA’s FAQ lists private for-profit firms and individuals as potentially eligible for ordinary loans, not subgrants. All applicant, site and program conditions still apply.
Does the end of fieldwork end the ownership requirement?
Not necessarily. Confirm the subgrant agreement’s actual period of performance, including amendments, with the administrator. Cleanup controls or monitoring may continue after it ends.
Sources & further reading
Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.