Separate the cabinets from the lift
Request a site and lift plan showing the licensed staging area, crane setup and travel locations, swing radius, load path and any area over adjoining property. Ask for the maximum height of the boom, attachments and suspended load throughout the operation, including setup and dismantling, and the ground elevation at each relevant position. The finished cabinet height is not a substitute for the highest temporary lift envelope.
Have the developer and qualified crane contractor check the plan against overhead lines, buried utilities, access, ground-bearing capacity and neighboring uses. Ask who will secure any additional access or overflight rights. If the crane location, height, dates or configuration change, require the responsible party to reassess the plan and any FAA submission before the changed operation.

Determine whether FAA notice is required
Under 14 CFR 77.9, notice is required when the FAA requests it or for specified construction or alteration, including work more than 200 feet above ground level at its site and work exceeding applicable sloping surfaces near certain airports and heliports. Other triggers and specific exceptions also apply. A crane can require notice below 200 feet; proximity to an airport alone does not establish that every crane requires a filing. Have the project team assess the actual location and full temporary height against the rule, including the relevant airport or heliport and its applicable surface.
When notice is required under section 77.9, section 77.7 calls for FAA Form 7460-1, Notice of Proposed Construction or Alteration, generally at least 45 days before the proposed start or the date a construction permit application is filed, whichever is earlier. The regulation provides an emergency exception to the advance period for specified immediate work. Build time for the FAA review and any revisions into the construction schedule. The FAA makes its aeronautical determination; submission of a form is not itself a finding that the proposed operation presents no hazard.
Name the responsible project party
Ask the developer to name one entity and contact responsible for collecting the lift data, deciding whether notice is needed, making any required submission and coordinating with the crane contractor and FAA. The developer may assign that work to its construction contractor or another qualified party, but the license should say who is accountable to the owner and who pays. Confirm who is the actual proponent for the operation; a private agreement does not transfer a regulatory obligation by itself.
Request a copy of the assessment, any filing and FAA determination, and require prompt notice of changes or FAA conditions relevant to the operation. Ask the project team to check whether the temporary crane needs a separate notice or amendment for its actual configuration rather than assuming any review of the permanent battery equipment covers it. Also ask about applicable state, local and airport requirements.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut the staging arrangement in writing
Have counsel describe the precise licensed area and access route, permitted activities, dates and extension process. Address survey and pre-use condition records, soil and pavement protection, traffic, fencing, security, insurance, indemnity, damage repairs, removal of equipment and debris, and restoration and inspection at the end. Identify who can enter and whether subcontractors may use the area.
Set a practical hold point before crane work: the designated project party supplies the final lift plan and evidence of any required FAA notice and response, and confirms applicable conditions and other approvals are addressed. Agree what happens if the operation changes or is delayed. Sunland welcomes nationwide land and existing project inquiries; share the location, approximate acreage, your relationship to the property and the requested staging use, and provide plans privately if requested.
Questions landowners ask
Does every temporary crane need an FAA filing?
No. The project team should assess the actual operation under 14 CFR 77.9. Notice can be required below 200 feet near certain airports or heliports, or when the FAA requests it; other triggers and exceptions also apply.
Can the battery cabinet height be used for the crane assessment?
The permanent cabinet height does not describe the highest point of the temporary operation. Ask the crane contractor for the complete lift envelope, locations and ground elevations for assessment.
Does the landowner have to file the notice?
The rule applies to the person proposing the covered construction or alteration. Identify the actual proponent and name the project party responsible for the assessment and any filing in the license. A contract allocation does not itself change regulatory obligations.
Sources & further reading