California landowner guide

Delivering a battery storage pad after a compost operation ends

A landowner asked to deliver a battery storage pad may still have a regulated compost operation on the proposed footprint. Stopping incoming loads is not the same as completing site restoration. Identify the operator and enforcement agency, understand the site’s requirements and document the condition of the whole affected area before promising possession.

Could my land work?

Obtain the compost site records and ask the operator and enforcement agency to confirm the restoration scope and schedule. Under 14 CCR section 17870, the operator gives written notice of intent to restore at least 30 days before restoration begins, while operators and owners must provide necessary restoration. Document residue handling, machinery, structures and drainage, and negotiate clear completion evidence and possession conditions for the battery project.

Identify the operation and the responsible agency

Confirm the operator, landowner, site boundaries, materials handled, regulatory tier and current status. CalRecycle’s Solid Waste Information System (SWIS) can identify a site, its operator, enforcement agency, inspections and records; use it as a starting point and obtain the actual permit or notification, inspections, orders and amendments. Ask the enforcement agency (EA), usually the local enforcement agency (LEA), which requirements apply. CalRecycle acts as EA in some jurisdictions without an LEA.

Section 17870 applies to compostable materials handling operations and facilities in its regulatory chapter. Some activities are excluded under section 17855, and a site may have more than one regulated use. Verify the classification instead of assuming that every pile of organic material has the same rules. Where applicable, request the Report of Composting Site Information and its proposed restoration activities, along with lease and title documents that govern access and handback.

Illustration of a land parcel and surrounding landscape

Separate notice from the shared restoration obligation

Section 17870(a) requires the operator to give the EA written notice of intent to perform site restoration at least 30 days before beginning restoration. Ask for the dated notice, delivery evidence and any agency response, and confirm the planned start. A landowner’s conversation with the developer does not replace the operator’s notice. The rule does not say that the 30-day notice alone authorizes battery construction or establishes restoration completion.

Section 17870(b) requires the operator or operators and owner or owners to provide site restoration necessary to protect public health, safety and the environment. Section 17870(c) makes the operator responsible for ensuring specified procedures are performed upon completion of operations and termination of service. A lease can allocate work and costs between parties, but it does not erase regulatory responsibilities. Ask the EA what inspections, documentation, permit or notification changes and other steps it expects for this site; do not assume the regulation prescribes a universal closure certificate.

Document what was removed and what remains

Section 17870 calls for grounds, ponds and drainage areas to be cleaned of all residues, including compost materials, construction scraps and other operations-related materials, with residues legally recycled, reused or disposed of. Machinery must be cleaned and removed or securely stored; remaining structures must be cleaned of compost materials, dust, particulates and other related residues. Secure storage is a regulatory alternative to removal, but it may not deliver the clear pad the developer expects.

Walk the area with the operator and map former piles, processing pads, ponds, ditches, drains, stockpiles, equipment and access. Request dated photographs, inventories, hauling and receiving records, recycling or disposal receipts, equipment disposition and documentation of cleaned structures and drainage areas. Compare evidence with the agreed handback plan and ask the EA what it will review. If conditions suggest a release or contamination, have a qualified environmental professional assess appropriate investigation; visible cleanup and receipts alone do not establish subsurface condition.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Condition the battery handoff on an achievable result

Overlay the battery containers, foundations, access, trenches, staging, grading and drainage on the compost footprint and surrounding water controls. Determine who maintains ponds and drains during restoration and whether changing or removing them requires separate water-quality or other agency review. Ask the regional water board and local authorities as appropriate; compost restoration does not itself approve a new drainage design or battery project.

Negotiate a dated handback standard, boundaries, responsibilities, access for the operator and EA, evidence, inspection process, cost allocation, schedule and remedies if restoration is delayed or incomplete. Make possession and ground disturbance conditional on the agreed evidence, resolution of remaining rights and any required agency actions and permits. If the battery developer needs early investigation access, define it separately and protect ongoing restoration and drainage.

Compost site restoration is distinct from landfill closure and postclosure maintenance. If the property also contains a disposal site, landfill, buried waste or other regulated activity, investigate its separate obligations rather than assuming compost restoration resolves them. Sunland reviews battery storage land opportunities; an authorized owner can share the approximate location, acreage, known compost history and proposed handback privately.

Questions landowners ask

Who gives the restoration notice?

For an operation or facility subject to section 17870, the operator gives written notice to the EA at least 30 days before restoration begins. Owners and operators also have the restoration responsibility described in the rule.

Can the owner deliver the pad as soon as the notice period ends?

Not on notice alone. Establish the required restoration and site-specific agency process, document the agreed handback condition and resolve other approvals before possession or ground disturbance.

Must every machine be removed?

Section 17870 requires machinery to be cleaned and removed or securely stored. The parties may agree that removal is necessary for the battery pad and access.

Sources & further reading

14 CCR section 17870 and CalRecycle compost and enforcement materials checked November 16, 2026 Pacific. Confirm applicability and site-specific requirements with the enforcement agency. Local rules and program details can change. Check the requirements for the actual project.