Identify the facility and the transaction
This guide addresses an operating California solid waste landfill with a full solid waste facilities permit. CalRecycle says active disposal facilities generally require a full permit unless the LEA grants an exemption. Confirm the actual permit tier, facility boundaries and responsible agencies before using this framework; other tiers have different notice provisions.
Gather the deed, survey and legal descriptions, current permit and amendments, Report of Facility Information (RFI), site operating plan, closure and postclosure plans, financial assurance instruments and existing operating and land agreements. Identify the fee owner, any lessee, the landfill operator and proposed battery buyer or tenant. CalRecycle describes an owner as including a person with a fee, leasehold or other possessory interest in property presently used as a solid waste facility. An operator has a separate legal role. Ask counsel and the LEA how those definitions apply to the actual interest and land.

Choose what remains and what changes
If the current parties retain the landfill while a distinct area is offered for battery storage, compare the proposed legal boundary with the permitted facility and land presently used for waste operations. Establish whether the battery party receives only project rights or an interest affecting the facility. Even where the landfill operator stays, the agreement and physical layout may require agency review or changes to plans. Do not presume that a partial parcel is outside the facility simply because no waste is visible there.
If the deal transfers covered ownership or operation, identify the incoming party, its actual responsibilities and the anticipated transfer date. Confirm that it can operate within permit conditions and carry the required assurance. A battery developer should not be assumed to accept the landfill business. If the proposal changes landfill design or operation, or contemplates closing a unit, ask the LEA about the separate permit and closure pathways before setting the construction schedule.
Plan the notice and agency review
For a covered planned transfer, California Public Resources Code section 44005 calls for the owner or operator to notify both the enforcement agency and CalRecycle in writing 45 days before the anticipated transfer. Title 27 section 21630 addresses planned transfers of ownership or operation of the facility or land and the information to submit. Review the actual transaction and land in use with the LEA and counsel to determine whether and when notice applies; do not treat every battery lease as an automatic 45-day transfer.
CalRecycle guidance calls for identifying the incoming owner or operator and providing its contact information. The anticipated party supplies evidence of financial assurance and operating liability requirements, a signed affidavit concerning the permit and submitted information, and RFI amendments reflecting the change. Assign preparation and delivery of each item and retain copies and agency responses. The LEA reviews whether the facility can operate under the existing permit and RFI; for a landfill the process includes CalRecycle confirmation concerning applicable financial assurance requirements.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSeparate a transfer from a facility redesign
A name change on a permit is not approval to change waste operations. Section 21670 states that its owner or operator change process does not authorize changes to other permit aspects or replace a permit review or revision. If the facility will not operate in compliance with the existing permit or applicable requirements, section 44005 calls for the new owner or operator to apply for a revised or modified permit.
Ask the LEA whether the battery proposal changes the landfill’s design, operation or RFI, and what application, review and timing are needed. CalRecycle notes that proposed design or operational changes may require modification or revision of a full permit. Coordinate separately with the regional water board, air district, local planning and other authorities as applicable. A transfer notice, a proposed site plan or a private contract does not itself authorize construction or a redesigned landfill.
Protect operations and financial assurance
Overlay the battery pads, fencing, roads, trenches, utility connections and staging areas on the permit maps. Show active and planned waste cells, buffers, drainage, gas collection, leachate systems, monitoring points and routes for waste vehicles, sampling, repair and emergency access. Ask the landfill engineer and operator to identify clearances and operational conflicts, including future cell development and closure work. Verify uncertain boundaries before intrusive work.
CalRecycle identifies closure, postclosure maintenance and operating liability as landfill financial assurance categories. Review the actual instruments, costs, covered parties and dates with the responsible parties, providers and agency. Identify how assurance and access continue through any handoff and obtain agency confirmation where required; do not assume a sale, lease or private allocation releases existing duties or automatically transfers an instrument.
Set conditions for possession and review
With counsel, allocate notices, agency contacts, records, studies and costs. Define the delivered parcel and access rights, continuing waste operations, inspection and repair access, utility routes, insurance, damage and restoration obligations. Tie possession and construction to the agreed evidence and applicable agency actions; address delay, redesign or termination if the proposed arrangement cannot proceed. Coordinate the schedule with the landfill operator and avoid relying on a filing as proof of approval.
Owners and authorized representatives nationwide can ask Sunland to review a battery storage sale or lease or an existing project agreement. Share the location, approximate acreage, relationship to the property and operating landfill status; provide detailed maps and permits privately as appropriate. Sunland may contract with an owner and later assign the agreement to a specialist developer. Have counsel review the actual assignment, access and closing terms.
Questions landowners ask
Does a battery lease automatically transfer the landfill permit?
No. The parties, land and rights granted matter. Ask the LEA and counsel whether the specific arrangement changes a regulated owner or operator interest and what notice or other review applies.
When is transfer notice required?
For a covered planned transfer under Public Resources Code section 44005, written notice goes to the enforcement agency and CalRecycle 45 days before the anticipated transfer. Confirm the facility tier, transaction and applicable requirements with the LEA.
Can a permit transfer approve a new battery layout?
Not by itself. A facility design or operation change may require a separate RFI, permit modification or revision and other agency reviews. Ask the LEA to assess the proposed layout.
Sources & further reading
Sources checked 2026-11-18. Local rules and program details can change. Check the requirements for the actual project.
- California Code of Regulations: 27 CCR 21630, owner and operator changes
- California Code of Regulations: 27 CCR 21670, enforcement agency review
- California Department of Tax and Fee Administration: Public Resources Code section 44005
- CalRecycle: Change in owner or operator guidance
- CalRecycle: Solid waste facility permits fact sheet
- CalRecycle: Permitting landfills and disposal sites