Define what the entry request allows
Ask for a scaled plan showing each proposed boring or test pit, equipment and staging areas, routes, dates and any related ground disturbance. Ask the geotechnical contractor to explain its scope and who will coordinate utility identification. Compare the plan with operations, traffic, tenant areas and existing access rights. A site walk or records review can be considered separately from permission for borings.
This guide addresses California property in USA North 811’s service territory, including Sacramento, Alameda, Fresno and 46 other counties. Its published list identifies the nine counties served by DigAlert instead, including Los Angeles and San Diego. Confirm the correct notification center for the site; USA North also serves Nevada, whose rules are outside this guide.

Compare the ticket with what the site knows
Ask the contractor for the ticket and its defined work area, the notified member list, each response and any required field-meeting results. USA North’s California field guide says every utility operator on the ticket must respond and any required on-site meeting be completed before digging. A response may mark facilities, provide location information or report no conflict for the specified area; it is not a map of every buried facility on the parcel.
USA North explains that notified members locate the facilities they own and operate, while private lines may not be marked. Ask the contractor to check what each response covers and resolve incomplete or unclear responses with the member and notification center. A ticket or a clear response is not, by itself, permission to proceed or proof that private lines do not exist.
Find the private and tenant records
Collect available as-built drawings, surveys, prior locate reports, maintenance and repair records, site plans and information from the facility manager and tenants. Consider electrical feeders, gas, water, sewer, fire lines, communications, process piping, drainage and abandoned or undocumented facilities. Compare the evidence with the proposed work and field conditions; old plans can be incomplete or inaccurate.
Identify who owns or controls each known system and who can authorize access to records and equipment. Ask the developer to engage a qualified private utility locator where needed and agree on the area, systems and deliverable. Some lines may not be reliably locatable by a given method. Have the contractor and locator document limitations and discrepancies, and consult the responsible system owner before deciding whether to move, defer or omit a proposed boring.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMake a conditional entry decision
The owner can negotiate a staged authorization: allow a site walk and record review first, then consider specific ground-disturbing locations after the site team has reviewed the utility information and unresolved issues. A revised location or expanded work area needs a fresh review of its scope and applicable notification requirements. If a conflict remains unresolved, defer the affected work until the responsible parties establish an acceptable plan.
Have counsel review the entry agreement and existing tenant and utility rights. Identify the contractor and site contact, authorized locations, access hours, required tenant coordination, responsibility and payment for private locating, insurance, damage response, restoration, reporting and a process to stop or change work. Written allocation of responsibilities helps the owner assess the request; it does not replace the excavator’s applicable legal duties.
Sunland reviews battery storage opportunities throughout the United States, including land for sale or lease and existing project agreements. An owner or authorized representative can share the location, approximate acreage, operating uses and nature of the requested investigation; provide detailed utility records privately if requested.
Questions landowners ask
Does an 811 clear response mean there are no buried utilities?
No. It addresses the responding member’s facilities and the ticketed area. Owner- or tenant-controlled facilities and other gaps still need review.
Who should arrange a private locate?
Agree on responsibility and payment in the entry agreement. The developer and excavation contractor should coordinate with the site owner, tenants and responsible facility owners; the appropriate scope depends on the property and work.
Can I allow a site visit but defer borings?
Yes. An owner can negotiate staged access, subject to existing rights, and consider ground-disturbing work after reviewing the proposed locations and utility information.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.