Check the company name and the permitted use
Start with the instrument that grants use of the crossing. Check the names of the lessees, the permitted uses, the land covered and any conditions on sharing or transfer. Put those details next to the legal name of the company that would use the crossing after your sale, lease or assignment.
If the battery company is absent from the state lease, ask what instrument or other authority would support its use and whether the state agency requires an approval. A private agreement can address terms between the companies. Ask for the state crossing documents as well before committing to access or paying for rights in the deal.

See what changed in the Athos state lease
On October 17, 2024, the California State Lands Commission approved an amendment to add Athos Storage, LLC to an existing right-of-way lease on state school land in Riverside County, alongside SE Athos I, LLC and SE Athos II, LLC. The authorization specified that the change to the lease’s basic provisions would be effective that day and that the other lease terms would remain in force.
The commission report described a battery project on private land that would use improvements already within the state lease premises. It anticipated no new infrastructure within those premises. An April 2026 commission report listed all three companies as lessees. The two records document the commission’s authorization to add a separate battery company to an existing state lease and the names the agency listed later.
Settle shared responsibilities before closing
Ask which companies can enter, use and maintain the crossing and how they divide costs. Check the private shared-use agreement for those responsibilities and compare it with the current state lease. Clarify who will obtain any outstanding agency or utility approvals and what documentation the parties expect at closing.
If your buyer would use a new legal entity, ask the agency about that specific change. In April 2026 the commission separately authorized execution of a consent to encumber the Athos lease, with the consent to take effect once all parties signed. If a transaction includes financing or a transfer, ask which approvals cover each step and request the documents that show those approvals took effect.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your property or existing agreement
Sunland welcomes inquiries from owners and authorized representatives nationwide about selling or leasing battery storage property or assigning an existing agreement. Share the general property location, your role and the transaction you are considering. Keep signed leases, maps and other private records out of your initial message.
Questions landowners ask
Why check a state crossing lease when the battery is on private land?
The battery parcel and the crossing can have different owners and separate agreements. Verify who can use the state crossing under the actual lease and any approved amendments.
Did the battery company replace the solar lessees in the Athos example?
The October 2024 approval authorized adding Athos Storage, LLC to the lease, and the April 2026 staff report listed both solar companies and Athos Storage as lessees.
What should a buyer ask for if it will use the same crossing?
Ask for the current signed state lease and amendments, the relevant shared-use agreement and any consents for the buyer’s use or transfer. Confirm with the agency which steps are still open.
Sources & further reading
Official commission voting records and item reports checked November 21, 2026. Verification covers the recorded votes and public reports. The signed instruments and any subsequent changes remain unverified. Local rules and program details can change. Check the requirements for the actual project.
- California State Lands Commission, October 17, 2024 voting record, consent item 50
- California State Lands Commission, October 17, 2024 item 50, Athos right-of-way lease amendment
- California State Lands Commission, April 7, 2026 voting record, consent item 61
- California State Lands Commission, April 7, 2026 item 61, named lessees and separate consent to encumber