Determine whether the land is part of the project
Obtain the recorded CTCAC regulatory agreement and amendments, allocation and project identifiers, deed, title report, survey and original site plan. Have counsel identify the project’s legal boundary, current owner and authorized decisionmakers. This rule addresses a tax-credit project owner’s sale of a portion of vacant or unused land; it is not a universal rule for every California apartment property or every transaction near affordable housing.
Check the remaining regulatory term and any other recorded restrictions with CTCAC. The committee monitors compliance throughout the project’s regulatory period, including after the initial 15-year federal compliance period. Do not assume land is free of project restrictions because tax credits have been claimed or the first 15 years have passed. Identify any partner, investor or management authority needed to make and carry out the proposed commitment.

Map the sale against the homes that remain
Ask a surveyor and the housing operator to map the proposed parcel together with the battery enclosure, foundations, construction staging, access, cables, drainage and utility easements. Overlay housing buildings, resident parking, pedestrian routes, recreation areas, landscaping, emergency access and existing infrastructure. A strip without a building can still support resident use or future obligations under the approved project.
Ask whether the remaining housing can maintain its required amenities, access and services during construction and throughout battery operation. Identify potential noise, screening and safety questions for the developer and local authorities. Confirm whether subdivision and permanent rights across retained land are needed. Do not describe an area as disposable merely because it appears vacant on an aerial image.
Compare the two proceeds commitments
Section 10338(a)(5) requires the project owner to commit either to contributing the sales proceeds to a new multifamily affordable housing deed-restricted project or to reducing rents at the existing property by the aggregate amount of the sales proceeds. The first option is a contribution, not a loan. Compare whether there is an appropriate new project and authority to make that contribution with the practical implications of a rent-reduction plan at the existing property.
Present the actual offer and proposed plan to CTCAC. Ask how it will determine the relevant proceeds amount, whether and how transaction costs are treated, the required timing and documentation, and how an approved rent reduction should be implemented and verified. The rule does not itself provide every accounting or scheduling detail. Do not assume a deduction, payment schedule or substitute fee; obtain the committee’s direction for the transaction before calculating what the sale means for the project.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSeek written approval and separate other consents
Provide CTCAC with the project identifier, recorded agreement, proposed legal description, site plan, purchase terms and the proposed proceeds commitment. Ask the committee what application, supporting documents, recording and other steps it requires. The rule calls for the Executive Director’s prior written approval before the sale. A preliminary discussion, submitted request or conditional purchase offer is not that approval.
Review the mortgage, deed of trust, housing assistance or other public funding agreements and partnership documents. A lender release, HUD or other housing-agency consent, investor approval, subdivision and title work may be separate from CTCAC review. If a HUD-insured multifamily mortgage covers the parcel, ask the servicer and HUD about a partial release. Do not assume the land-only battery buyer must satisfy every whole-project transferee qualification or capital-needs requirement; ask counsel and CTCAC which provisions actually apply.
Compare retaining the land or another proposal
If the required proceeds commitment, resident impacts or consent process makes a sale unattractive, consider retaining the land or evaluating a different parcel. A smaller footprint may preserve access or amenities, but it still needs review against the project’s actual boundary and restrictions. Ask the developer to show its complete rights and design rather than pricing only the fenced pad.
A lease or easement is a different proposed interest and must be reviewed under the regulatory agreement, financing and other applicable requirements. Section 10338(a)(5) addresses a sale; it should not be used to conclude that every lease has the same proceeds requirement or that a lease automatically avoids project restrictions. Ask CTCAC and counsel about the specific terms before granting an option, access or possession.
Make the agreement conditional and reviewable
Have counsel make the sale contingent on the necessary written CTCAC approval, an agreed proceeds plan and other required consents and title arrangements. Identify who prepares the application, pays for survey and studies, and coordinates the housing and battery teams. Define permitted early access, responsibility for damage, closing conditions and what happens if the parcel must change or an approval is denied or delayed. Ask a project tax adviser to assess the actual federal and state tax consequences without assuming recapture or an exemption.
Owners and authorized representatives nationwide can ask Sunland to review a battery storage sale, lease or existing project agreement. Share the location, approximate acreage, your authority and the known CTCAC project connection; provide regulatory and financing documents privately as appropriate. Sunland may contract for land and later assign its interest to a specialist developer, subject to the agreement. Assignment does not itself grant authority to sell restricted project land.
Questions landowners ask
Can the owner distribute the sale price as ordinary profit?
Do not assume so. For a covered sale, section 10338(a)(5) requires a commitment either to contribute the sales proceeds to a new deed-restricted multifamily affordable housing project or reduce rents at the existing property by the aggregate proceeds. Ask CTCAC about the actual calculation and plan.
Does a lease avoid CTCAC restrictions?
A lease is a different transaction and the sale provision does not establish the answer for every lease. Review the proposed rights with CTCAC and counsel under the actual regulatory and financing documents.
Is CTCAC approval enough to build the battery?
No. Lender and other housing consents, subdivision, local land-use and fire review, interconnection and other approvals may be needed separately.