Confirm the existing program and accounts
This guide concerns an existing PG&E NEM2A arrangement, in which one customer’s eligible meters share the output of an existing generator. Request the approved aggregation appendix, interconnection records, permission-to-operate date, application date and recent bills. List the generator and every benefiting meter, its parcel, service agreement number and customer of record.
Ask PG&E to confirm the actual program and legacy period. NEM2A closed to new applications after February 14, 2024. Some later net billing aggregation customers have been billed temporarily under NEM2A while a billing system is prepared; that does not itself establish NEM2 legacy eligibility. An old form or bill is not enough to settle the question.

Draw the parcel chain before and after
Prepare a before-and-after map showing the generator, each meter, parcel boundaries and intervening parcels, even those without meters. Add the proposed sale or lease footprint and identify who will own, lease or rent each parcel and who will hold each electric account. Attach deeds, leases and relevant recorded rights. A change in farm tenant may change control or account names even without a land sale.
The NEM2A tariff generally requires the generator and aggregated meters to be on the same parcel or an unbroken chain of contiguous parcels solely owned, leased or rented by the same customer-generator. Exceptions exist for certain separations, including public thoroughfares and specified easement or waterway circumstances. A typical access easement across another owner’s land should not be assumed to preserve the chain. Ask PG&E to assess the actual rights and map; a partial sale does not automatically end eligibility.
Plan the utility request and its sequence
If the same customer will keep the generator and change the load accounts, ask PG&E whether a rearrangement applies. If a new customer will take over the generator account and at least two existing load accounts, ask about a Change Party request. The form requires the revised arrangement to remain eligible; its rearrangement and Change Party worksheet applies when generator size is not increasing.
Prepare the documents and questions before closing. The form says a Change Party request can only be made after the new owner begins service as the new customer of record for the applicable services. Coordinate the start of service and submission with PG&E and the other party; do not promise final approval before that step. If a change makes a listed meter ineligible, the form calls for notice to PG&E and an updated appendix. PG&E may request the parcel map and ownership records.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landSeparate credits from remaining legacy
Ask PG&E for the expected true-up, account-by-account credit treatment and any change in electricity charges under the proposed handover. PG&E warns that changing the customer of record causes an early true-up and loss of banked NEMA credits. Adding or switching meters can also affect credits. Do not assume a balance transfers with the deed or is paid out at closing.
A remaining legacy period is a separate question. For a system eligible for the tariff’s 20-year transition period, transfer to a new owner, operator or account at the original location does not itself remove that eligibility. That alone does not establish eligibility of a changed multi-meter arrangement. Different cohorts have different periods, including a nine-year cohort, so do not assume every system has the same original period or remaining time. Ask PG&E to confirm both the period and the proposed arrangement.
Put the result into the transaction
With counsel, compare alternative boundaries and genuine retained rights against PG&E’s response. Address who requests and pays for account changes, handles outstanding bills and lost credits, and bears higher electricity costs if an expected arrangement is unavailable. Consider deadlines and what happens if utility review does not support the proposed handover. Review equipment ownership and any power purchase agreement separately.
Tell Sunland the California property location, acreage, proposed sale or lease area and whether an existing solar system and aggregated farm meters are involved. An inquiry does not commit your property or establish utility approval.
Questions landowners ask
Will a sale of one parcel automatically end aggregation?
Not necessarily. The specific parcel rights, account names and tariff exceptions matter. Give PG&E the before-and-after map for review.
Does keeping legacy treatment preserve my banked credits?
These are separate issues. Ask PG&E about both the applicable legacy period and the true-up and credit consequences of your specific account change.
Sources & further reading
PG&E tariff, program guidance and current listed form checked November 19, 2026. Form 79-1202 is dated March 2021. No individual arrangement or property records were reviewed. Local rules and program details can change. Check the requirements for the actual project.