Start with the land that will actually be used
Put the parcel boundaries, existing enrolled fields and proposed solar fence on one map. Add roads, construction staging, drainage, utility routes, wells and the fields you expect to continue irrigating. A project can affect less than an entire assessor parcel, and a parcel number alone may not describe the enrolled acreage.
The Board’s decision tree asks whether property is commercial cropland, whether it is irrigated regardless of water source, and whether it is covered under a separate order. Its definition includes land irrigated to produce commercial crops or pasture, including immature crops, as well as nurseries and certain managed wetlands. A separate order covering managed applications to cropland can make additional ILRP coverage unnecessary; identify the actual order rather than assuming a solar permit substitutes for one.
Review each area with the current grower, coalition and Board. If irrigated commercial production remains outside the fence, ask how those acres will remain covered, who is responsible and how maps and reports should be updated. Do not remove all acreage merely because a portion is proposed for solar.

Distinguish fallowing from a completed change of use
A field left idle while a developer studies a site can return to crops if the project does not proceed. Treat temporary fallowing as a question for the coalition and Board, not proof that coverage has ended. Provide the dates, irrigation and crop history, intended future use and current enrollment information; ask what reporting and fees apply during the idle period.
A permanent conversion is a different factual question. When the footprint has actually stopped commercial irrigated agricultural use, give the coalition and Board a revised map, effective date and evidence of the change. Ask how to update membership or claim an exemption for the affected land. The Board says its staff verifies exemption claims. Keep the response and continue required coverage until the appropriate change is confirmed.
If the project allows crops or irrigated pasture beneath or around panels, assess the real activity rather than the project label. Likewise, a return to commercial irrigation after a failed project or at lease end calls for a fresh coverage check before farming resumes.
Identify the applicable order and coverage route
The Central Valley Board lists separate coalition orders by watershed or area, including the Eastern San Joaquin River Watershed order R5-2012-0116 and the Western Tulare Lake Basin Area order R5-2014-0001, each with revisions. The Board also lists other geographic orders, a Sacramento Valley rice order and an individual grower order. Determine the applicable area and current amendments for the fields instead of borrowing another farm’s order.
A grower can join the designated coalition for the location or seek individual coverage under Order R5-2013-0100. Coalitions assist members with regional monitoring and reports, but members remain responsible for compliance and good standing. An individual grower submits a notice of intent and fee to the Board and bears individual monitoring, reporting and compliance responsibilities. The individual notice is not the application for coalition membership.
Obtain the enrollment record, covered acreage map, current fee status, required farm plans and pending reports. Ask the coalition which updates, supporting documents and deadlines apply to this particular change, and obtain written confirmation of the resulting coverage.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPlan the handoff for a sale, lease or assignment
For a sale, identify the closing date, purchaser, acreage and any farming that continues after closing. The seller and buyer should coordinate with the coalition or Board about ending or updating one enrollment and securing any needed coverage for the next operator. Do not assume coverage automatically follows title or that closing erases prior reporting obligations.
For a solar lease, the owner may retain title while the developer controls the project footprint and a tenant farms the rest. Identify who operates each area and who will pay fees, maintain plans, submit reports and respond to the coalition. The private lease can allocate costs and cooperation, but it does not itself determine the Board’s regulatory obligations.
An assignment changes the company holding project rights; it does not necessarily change ownership or the person farming retained acreage. Require notice and updated contacts, and coordinate any actual operator or land-use change with the coalition or Board. Address outstanding fees, records and cooperation if the project is transferred, terminated or returned to agriculture.
Make the map and handoff part of the solar discussion
Ask the developer for the proposed footprint and phasing, including when farming must stop and when construction would begin. Compare those dates with the farm lease and reporting cycle. Provide for access to wells and retained fields, management of runoff and responsibility for records and agency communications.
Share the location, approximate acreage and current use through the form on this page. Tell Sunland America which land you want to keep farming and whether you are considering a sale or lease. An inquiry does not commit you to a transaction or replace a determination by the coalition or Water Board.
Questions landowners ask
Does signing a solar option end ILRP coverage?
No. An option is a proposed transaction; assess actual land use and maintain applicable coverage while consulting the coalition and Board.
Can temporarily fallowed acreage be removed automatically?
Do not assume so. Ask the coalition and Board how the field’s history, intended use and idle period affect enrollment, reporting and fees.
What if only part of the farm becomes solar?
Map the changed footprint and retained fields separately. Confirm how to update the affected acreage while maintaining required coverage for commercial irrigated land that remains.
Is coalition membership the only way to obtain coverage?
No. A grower may seek individual coverage under the individual general order, with direct monitoring, reporting and compliance responsibilities.
Does an exemption claim approve itself?
No. The Board says staff verifies exemption claims. Provide supporting information and ask for confirmation of the status of the affected land.
Does a sale, lease or assignment automatically transfer coverage?
Do not assume it does. Identify the owner and operator of each area and coordinate the needed enrollment changes with the coalition or Board.
Sources & further reading
Sources reviewed November 16, 2026 Pacific. This guide addresses the Central Valley Regional Water Board program, not every California region. The decision tree and program guidance are screening tools; confirm the applicable order, amendments and acreage-specific treatment with the coalition and Board. A proposed solar use alone does not establish exemption or approval under another program. Local rules and program details can change. Check the requirements for the actual project.
- Central Valley Water Board: Irrigated Lands Regulatory Program
- Central Valley Water Board: ILRP coverage decision tree
- Central Valley Water Board: Regulatory information and adopted orders
- Central Valley Water Board: ILRP frequently asked questions
- Central Valley Water Board: Eastern San Joaquin watershed orders
- Central Valley Water Board: Western Tulare Lake Basin orders
- Central Valley Water Board: Coalition group information
- Central Valley Water Board: Apply for individual coverage