Find the crossing before fixing the layout
Ask the developer for a map showing the parcel, panels, access roads, underground or overhead cables, construction areas and the connection route beyond the parcel. Compare it with deeds, title records, surveys and any known easements or existing crossing documents. Mark the proposed work where it may meet a canal, pipeline, tunnel or other State Water Project facility and its right-of-way. For example, Stanislaus County’s early consultation for the proposed MID Valley Power solar project describes two overhead collection lines at one California Aqueduct crossing, subject to DWR approval and permitting.
The California Aqueduct includes canals, pipelines and tunnels, so a buried facility may not be apparent from a site visit. A property line, aerial image or preliminary map alone does not establish the extent of DWR’s rights. Ask DWR to help identify its facilities and confirm the affected right-of-way; request relevant as-built information through its program.

Ask DWR about the proposed work
DWR reviews third-party installations and alterations for conflicts with State Water Project facilities and operations. Its listed examples include roads or bridges over pipelines or the aqueduct, above- or below-ground utility crossings, grading and construction on or near the right-of-way. A DWR encroachment permit is written authorization for specific facilities within the State Water Project right-of-way.
Contact the program at swp.encroachments@water.ca.gov or 800-600-4397. Send the location, parcel information and a preliminary drawing of the road or cable, access, staging and construction method. Ask whether the work requires a permit, what existing records apply, and what alternatives or further information DWR wants to see. DWR evaluates whether a proposal is consistent with project operations, maintenance and future work; approval is not automatic.
Develop the crossing with the right information
Have the developer and its qualified engineer prepare the plans DWR requests, including the proposed alignment, dimensions, construction and access areas and relationship to existing facilities. DWR’s plan guidance says to request as-builts from the program and to contact DWR about pothole procedures. It also states that utilities crossing under a State Water Project pipeline are to be installed by horizontal directional drilling or boring or jacking. Confirm applicable requirements for the actual facility and design with DWR before selecting a method.
DWR’s environmental guidance asks applicants for location and footprint maps, a project description, disturbance and access information, and applicable environmental review and compliance documentation. Ask which materials and other agency approvals are needed for this particular proposal; a DWR permit does not replace other required approvals.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAddress timing and responsibility in the agreement
Discuss feasible alternatives and review timing with the developer before accepting a fixed route. Have your attorney review the option, lease or easement for responsibility for engineering, applications, costs, access and changes if DWR requires a different design or denies the proposal. DWR’s FAQ notes that permit conditions may require relocation or removal at the permittee’s expense for future State Water Project work, and that rights granted by a permit do not transfer without DWR’s written consent. The permittee must also notify DWR in writing if its interest in the property subject to the permit is sold or transferred.
Existing access or ownership does not by itself establish permission for the proposed crossing. A person asserting an exemption based on an existing property interest or agreement must submit documentation to DWR for its determination. People holding an exemption under DWR’s regulations must still submit plans for DWR review and comment before work in the right-of-way and comply with its written requirements. Otherwise, obtain required written authorization before work and follow the permit conditions. Sunland welcomes land and existing project inquiries nationwide. Share the location, approximate acreage and your relationship to the property; provide title and crossing documents privately if requested.
Questions landowners ask
Does every solar project near the California Aqueduct need a DWR permit?
Not necessarily. The need depends on the location and work proposed. Contact DWR with the project details to identify its right-of-way and determine the applicable review.
Can an existing road crossing be used for a solar project?
Do not assume so. Provide DWR with the existing authorization and the proposed use, including construction traffic and any changes, and ask what review or permission is needed.
Can a cable be buried under a State Water Project pipeline?
DWR’s plan guidance specifies horizontal directional drilling or boring or jacking for utilities crossing under a State Water Project pipeline. DWR must review the site-specific proposal and applicable requirements.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.