Identify the contract and the proposed footprint
Get the recorded Williamson Act or Farmland Security Zone contract, amendments, legal descriptions, maps and any notice of nonrenewal. Compare them with the full proposed solar footprint, including access, underground lines and temporary work areas. Ask the local government which acreage is covered, whether the contract is a Farmland Security Zone contract, and whether a partial rescission is practical for the actual layout.
A solar-use easement is a land-use restriction for photovoltaic facilities, not merely an agreement protecting sunlight. DOC says the easement generally has a 20-year term, or at the owner’s request a term of at least 10 years. Ask the county about the proposed instrument, renewal and termination rules, permitted activities and its relationship to the development lease before signing.

Ask the local government to initiate review
The landowner applies to the participating city or county. DOC expects local government to decide initially whether to pursue the process, develop the application with the owner and make the formal request. DOC says it will not opine on eligibility without a formal local request and a complete application supported by required evidence and analysis. Neither a developer’s interest nor an owner’s request obligates the county to proceed.
If the county will consider it, agree who will assemble studies, pay application costs and communicate with DOC. Ask for a written list of local steps, hearings, environmental review and separate land-use permits, and a realistic schedule. DOC says processing time is uncertain and depends on the completeness and quality of the application. The state eligibility determination is not itself permission to construct.
Build evidence of impaired agricultural use
Government Code section 51191 requires land to meet a statutory soil impairment test: predominantly soils with significantly reduced agricultural productivity for specified physical or chemical reasons, or severely adverse soil conditions detrimental to continued agriculture. The important-farmland map designation also matters. Prime farmland, unique farmland and farmland of statewide importance generally are excluded unless DOC, in consultation with the agriculture department, finds eligibility based on evidence of circumstances limiting agricultural use. Irrigation status alone does not change those designations for this purpose.
The county must require the owner to provide applicable evidence, including a narrative on limitations under the best currently available management practices, recent soil tests, water availability and quality analyses, and six years of crop and yield information. Gather farm records and qualified technical studies for the exact acreage. A low crop yield, dry year or map label alone does not establish eligibility; DOC makes the determination based on substantial evidence.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPrice the rescission and restoration obligations
Before mutual rescission, the county assessor determines the land’s current fair market value as if free of the contract restriction. DOC describes a rescission fee of 6.25% of that valuation for an ordinary Williamson Act contract, or 12.5% for a Farmland Security Zone contract, plus administrative fees. Ask the county for the applicable valuation, fee calculation and review process; the fee is not simply a percentage of solar rent or the restricted assessed value. Account also for any change in property taxes and project costs with the assessor and advisers.
The owner must submit a management plan covering soil management during the easement, minimizing impacts on neighboring agricultural operations and restoring the land to its previous general condition at project approval when the easement terminates. The local government must require implementation of the plan with DOC’s recommendations as part of project approval. For term or self-renewing easements, section 51191.3 requires the landowner to post a performance bond or other securities for restoration. Ask the county about the security amount, inspections, cost updates and release conditions, and make the developer’s removal, funding and default obligations enforceable in the lease. A developer’s promise alone does not replace the government requirements.
Compare alternatives before committing
Rescission with a simultaneous solar-use easement is one route, not the same as ordinary nonrenewal or cancellation. DOC also identifies local compatibility determinations and other contract removal routes as potential options. Availability, cost, timing and consequences differ. Ask the local government and counsel to compare them for the actual contract and project; do not assume an application or notice of nonrenewal alone clears the land for construction.
Sunland welcomes California solar land sale, lease and existing project inquiries. Share the approximate location and acreage and whether a Williamson Act or Farmland Security Zone contract applies; keep sensitive contracts and financial records private until needed for secure review.
Questions landowners ask
Can an owner apply directly to DOC for eligibility?
Start with the city or county holding the contract. DOC says it needs a formal local request and a complete supported application before it will opine on eligibility.
Does a solar-use easement remove all restrictions?
No. It replaces the rescinded contract acreage with a solar-use easement carrying its own restrictions and term, and the project still needs applicable approvals.
How much is the rescission fee?
DOC describes 6.25% of unrestricted fair market value for an ordinary Williamson Act contract and 12.5% for a Farmland Security Zone contract, in addition to administrative fees. Ask the county for the actual valuation and calculation.
Sources & further reading
Sources checked 2026-11-16. Local rules and program details can change. Check the requirements for the actual project.
- California Department of Conservation: solar-use easements
- California Government Code section 51191: eligibility and management plan
- California Government Code section 51191.3: restoration security
- California Government Code section 51255.1: mutual rescission
- California Department of Conservation: solar power and the Williamson Act
- California Department of Conservation: Williamson Act contract removal