Check which permit and security cover the project
Confirm with the county which zoning requirements apply and get the project’s special land use permit, approved decommissioning plan and any amendments. Clinton County’s consolidated zoning ordinance gives January 9, 2025 as the effective date for the amendment adding the utility-scale battery storage section.
Section 4.51.C.24.b calls for a cost determination by a third-party financial consultant or engineer chosen by the county and paid by the developer. It sets security posted with the county at 125% of the estimated cost and requires periodic updates at least every three years. Compare the latest estimate with the security actually in place. Ask the county to confirm the instrument, amount, scope and current status for this project.

Identify the owners and property that may be affected
Section 4.51.C.24.h authorizes the county to pursue the owner or operator or the landowner for decommissioning costs above the escrow amount. Its lien language refers to any real property those parties own. Ask counsel to identify the legal entities and their ownership interests and assess the scope of the provision under applicable law.
For example, the same company may own the leased battery parcel and a nearby parcel it intends to keep. Give counsel and the title company the deeds and lease so they can assess both interests. If the county has raised a shortfall, request its actual cost demand, any recorded lien and the current status before agreeing to a sale, refinance or release.
Agree who addresses a shortfall under the lease
Have counsel compare the county-held instrument with the tenant’s promises to remove equipment, restore the site and pay costs that exceed available funds. Ask who will provide updated estimates and evidence of continuing security, who pays for any required increase, and how you would be notified of a lapse or a county demand.
If the developer proposes an assignment, ask what documents show who takes on the removal and reimbursement obligations and what financial backing remains in effect. Put the dates and evidence the parties will need in the agreement. Your counsel can review how private payment and indemnity terms work alongside the county’s authority.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your property or existing agreement
Sunland welcomes inquiries from owners and authorized representatives nationwide about selling or leasing battery storage property or assigning an existing agreement. Share the general property location, your role and the transaction you are considering. Keep signed leases, title records and security instruments out of the initial inquiry.
Questions landowners ask
Does 125% security settle who pays every removal cost?
The percentage is based on the estimated cost. Compare the current estimate and security with the approved work and review any shortfall provisions in the county ordinance and your agreement.
Should I include nearby retained land in the review?
If the same party owns that land, tell counsel and the title company. The ordinance’s lien language refers to real property the owner, operator or landowner owns. The applicable scope and status depend on the facts and law.
How can I tell whether there is already a lien?
Ask the county about any demand and have the title company check the records for the relevant owner and parcel. Request the actual recorded instrument if one appears.
Sources & further reading
Clinton County’s current consolidated ordinance and adopted amendment were checked November 21, 2026. Local rules and program details can change. Check the requirements for the actual project.