Compare the licensed site with the rights being offered
This guide concerns a Connecticut licensed child care center, not a family child care home. Obtain the license and approved application, site plan and any later approvals from the operator. Compare the outdoor space identified for child care with a current boundary survey, the actual fence and gates, paths, equipment and emergency access. The existing fence may not mark either the legal property boundary or the full area the operator has rights to use.
Review the center lease, amendments, exhibits, easements and any shared-area or access rights with counsel. Identify who owns and controls the proposed pad and whether the landlord can grant exclusive possession, construction access or utility rights without the operator’s consent or a lease amendment. Overlay the pad, equipment clearance, permanent and temporary fencing, cable routes, truck turning and staging areas. Resolve overlaps in writing rather than assuming an unused edge is available.

Check outdoor space and approvals with OEC
Connecticut’s physical plant regulation, section 19a-79-7a, applies to child care centers and group child care homes. It requires access to at least 75 square feet of outdoor space per child using it at one time; the area must be fenced or protected for safety, and barriers must protect the play area from traffic and other hazards. Fences used to protect children from hazards generally must be at least four feet high, though that height provision does not apply to programs serving exclusively school-age children. Additional under-three rules require infant and toddler play space to be fenced; space licensed on or after January 1, 2025 must have a fence at least four feet high.
The same regulation requires OEC inspection and approval before use of indoor and outdoor space used for child care services as identified in the application. Plans and a written narrative for new construction, expansion or renovation must go to OEC before work starts, and OEC approval is required before newly constructed, expanded or renovated space is used. Ask OEC how these provisions apply to this specific boundary and replacement-space proposal; do not assume that moving a fence or using an alternate area is automatically approved. OEC may request written approvals from local building, health, zoning and fire officials.
Plan replacement space and construction phases
With the operator, calculate the remaining usable outdoor space for the number of children using it at once and assess safe routes, barriers, equipment, surfacing and supervision. If replacement space is needed, identify who controls it, when it will be available and the work and reviews needed before use. The regulation permits several types of outdoor space, but an available nearby area is not automatically a compliant replacement. Confirm the proposal and any temporary arrangements with OEC.
Map each phase from survey and installation through energization, maintenance and removal. Keep construction traffic, excavations, dust, equipment and deliveries separated from children, while preserving exits and emergency access. The regulation requires construction and alterations of structures to avoid hazards or unsafe physical or environmental conditions during operation. Establish the replacement area and obtain applicable approvals before reducing the existing area or giving the battery party possession; agree on a stop-work and contingency plan if the safe area becomes unavailable.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut conditions into the transaction
Whether the owner proposes a sale or lease, or an existing project holder proposes an assignment, identify the parties whose consent is required and make possession and construction conditional on documented property rights, any lease changes and applicable approvals. Set responsibility and funding for surveys, barriers, replacement play space, permits, insurance, access, maintenance, restoration and delays. Specify the boundaries and dates for each phase and how the center can continue safe operation. An assignment should also address which obligations and approvals can be transferred and which require new consent.
A child care review is separate from battery siting, building, fire, zoning and utility reviews. Ask the relevant authorities and utility about the actual design and interconnection; do not assume a fence or child care approval authorizes the battery. Sunland welcomes land and existing project inquiries nationwide. Share the property location, proposed transaction and a site plan without children’s names, photographs or other identifying information; provide sensitive documents privately only after removing personal information.
Questions landowners ask
Can the owner move the play fence to make room for the pad?
Not simply because the owner controls the parcel. Check the operator’s lease and approved site, assess the remaining space and safety, and confirm applicable OEC review and approvals before changing the boundary.
Does the 75-square-foot rule apply to every enrolled child at once?
The regulation specifies the number of children using the outdoor space at any one time. The operator should confirm its operating plan and any applicable conditions with OEC.
Is a nearby park automatically an acceptable replacement?
No. The regulation identifies parks among possible outdoor spaces, but the operator must assess access, safety and applicable review with OEC before relying on a replacement.
Can the battery party start work while approvals are pending?
Do not grant possession or start a phase that affects the center until the required rights, safe play arrangements and applicable approvals for that phase are in place. Separate battery and local permits may also be required.
Sources & further reading
Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.