Confirm the review route and your lot’s status
Give the Covert Township zoning administrator the project name and the parcel number for your lot. Ask for the application or approval number and confirm that the project is proceeding under the township’s Tier 2 special-use rules. Ordinance No. 122, effective October 7, 2024, lists Tier 2 battery storage as a special use in the Industrial District. Section 18.34(B)(1) defines participating lots as those on which the system may be established under a signed lease, easement or other agreement. Ask how the project plan identifies your lot and which records support that classification.
Michigan Public Act 233 provides a separate state certification route under specified conditions for storage with at least 50 megawatts of nameplate capacity and at least 200 megawatt-hours of discharge capability. If the project is proceeding through the Michigan Public Service Commission, ask for the docket number and the applicable sound rules and approval conditions.

Match the proposed waiver to one point on the plan
Ask for a dated site plan or sound measurement exhibit showing the battery site, your lot line and the point named in the waiver. Ask which locations the township would use to evaluate operating sound with and without the waiver. For example, if the point is near the part of the lot a tenant uses, ask where the next measurement would be taken and what it could show about sound at that part of the property.
The ordinance calls for a one-hour average of noise from the battery system, its components and related equipment to comply with the township’s Anti-Noise and Public Nuisance Ordinance No. 39, as amended. Section 18.34(B)(8) exempts shared lines between participating lots from the established maximum decibel levels. Applicants may submit equipment manufacturers’ sound ratings, and the township may require operating sound pressure measurements at sampled locations along participating lot boundaries. The provision lets the commission waive that measurement requirement at a particular point along a surrounding nonparticipating lot’s boundary. Ask the zoning administrator how that point relates to the sampling plan and which limits apply there.
Check the signatures and get the commission’s decision
Ask the township to identify whose written agreement it needs. If you rent your property to someone who occupies it, bring that up early. Plan for written agreement from the tenant as well. If ownership or occupancy is unclear, ask the township what documentation it needs.
Compare the draft with the ordinance and the mapped point. If the document also includes access rights, a release of claims or promises about future objections, have counsel review those terms before you sign. When the commission acts, keep its decision, any conditions and the plan it covers together. If the developer moves the point or revises equipment placement, ask the township whether a revised plan, written consent or a new decision is needed.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss battery storage property or an existing agreement
Sunland America welcomes inquiries nationwide from owners and authorized representatives considering a battery storage land sale, lease or assignment of an existing agreement. Share your role, general property location and the transaction you’re considering. Keep signed agreements, detailed maps and occupancy records private during initial contact.
Questions landowners ask
Can I sign the waiver if a tenant occupies the property?
Section 18.34(B)(8) calls for written agreement from the owner or owners and the occupant. Tell the zoning administrator who occupies the property and ask whose signature the township needs.
Does the waiver change the sound limit at my lot?
The waiver concerns whether the project must take a sound measurement at a specific point. The township can confirm the underlying limits and testing conditions under the project approval.
What if the developer moves the point after I sign?
Compare the revised drawing with the signed waiver and commission decision. Ask the township whether the location change requires updated consent or further commission action.
Sources & further reading
The adopted township ordinances and Michigan siting sources were checked November 22, 2026. Ask the township to confirm the review route, mapped measurement point and decision for your project. Local rules and program details can change. Check the requirements for the actual project.
- Covert Township Ordinance No. 122, zoning §§ 13.03(6), 18.34(B)(1) and 18.34(B)(8)
- Covert Township Anti-Noise and Public Nuisance Ordinance No. 39, as amended, §§ 3–4
- Covert Township Building and Zoning, zoning administrator and permit contacts
- Michigan Legislature, MCL § 460.1222(1)(c) and (2)
- Michigan Public Service Commission, renewable energy and storage facility siting