Locate the entire working system
Put the proposed solar boundary, construction limits and access roads on a farm map. Identify storage structures, transfer pipes and pumps, safety fencing, equipment turning space, runoff controls and routes for loading and hauling manure. Include areas needed for inspection and maintenance, not just the visible basin or tank. Compare the map with the developer’s proposed grading, trenching and fencing.
Collect existing permits, certificates, design drawings, operation and maintenance plans, nutrient management plans and inspection records. Ask the producer, tenant and manure hauler what access and seasonal work they need. A surveyor or engineer can help locate uncertain buried components before the footprint is fixed.

Compare continued use with closure
If the facility remains in use, discuss excluding it and sufficient working area from the project, and document how equipment and people can reach it during construction and operations. The county says permitted facilities must be operated and maintained under their operation and maintenance plans through the permit term. Ask the county about the status of the actual facility and any proposed modification.
Dane County states that at the end of a 20-year permit term an owner who wishes to continue using the facility must request a certificate of use, and an evaluation may be required. Its certificate also addresses certain unpermitted facilities. Confirm applicability and any conditions with the county; a solar agreement does not itself authorize continued operation.
Plan a permitted closure before construction
If the facility will no longer be used, Dane County says a manure storage facility closure permit is required. The county lists a closure application and checklist and requires plans certified by a professional engineer or engineering practitioner. Contact its Land Conservation Division before removing, filling or disturbing the structure to establish the applicable process and documentation.
Ask the engineer and county how stored material, transfer components, safety features and the final site will be addressed. Identify who will prepare and submit the application, perform and inspect the work, pay costs, and retain evidence of completion. Do not assume an empty or fenced facility has been properly closed. Other permits may also be needed.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landPut the decision in the transaction documents
Discuss the proposed boundary, preserved access or closure scope, cost responsibility, deadlines and what happens if review changes the layout. Address farm operations and replacement storage if needed while work proceeds. A lawyer can review the sale or lease, any farm tenancy and access rights against the actual plans and permits.
Sunland welcomes land sale, lease and existing project or agreement inquiries nationwide. Share the location, approximate acreage and your relationship to the property, and mention the storage facility and any proposed solar boundary. Provide plans privately if a reviewer requests them.
Questions landowners ask
Can the farm keep using the facility beside solar?
Possibly. Map the operating area and access and ask Dane County to confirm the facility’s permit or certificate status and the effect of any changes.
Is an empty facility automatically closed?
No. Dane County says a closure permit is required when a facility is no longer used. Ask the county and a qualified designer about the required work and documentation.
Do these county procedures apply throughout Wisconsin?
Local ordinances differ. DATCP describes the state framework; contact the relevant local authority for another property.