Confirm which procedure applies to the new item
Section 9.3(a) accounted for title and survey materials the investors had already reviewed. Section 9.3(b) addressed a qualifying new exception in a title update delivered after the agreement’s effective date. The exception had to fall outside the agreement’s permitted exceptions and meet a second criterion that is redacted in the public filing.
Give counsel both dated commitments and the document behind the exception. Review the full signed definition together. Check also whether the item is a mandatory removal exception under the agreement, which carries a separate cure obligation.

Track the objection, election and final response
The signed agreement gave the investor 10 days from the updated title commitment’s date, capped at closing, to notify the contributing member of an objection. If the objection was timely, the contributing member had 10 days after the investor’s notice to elect by notice whether to remedy the matter or take no action.
If the contributing member declined or let its notice period lapse, the investor had five days after receiving that election or after the response period expired to waive the matter and proceed or to terminate by notice. If the investor missed that deadline, the agreement treated the matter as accepted and allowed closing to proceed with it as a permitted exception.
Section 9.3(b) required the contributing member to extend closing as needed for the notice and response periods, up to the outside closing date. Have counsel apply the agreement’s notice delivery and non-business-day provisions to the deadlines and confirm when each notice counts as delivered.
Document any cure that carries past closing
The contributing member could elect a pre-closing cure, including asking the title company to insure over the matter. The clause allowed a cure after closing through the tenant only if leaving the matter open would have no material adverse effect on obtaining the applicable loan and the lease was amended to require the cure and waive related rent adjustments.
The agreement separately required the contributing member to remove or insure over mandatory removal exceptions at its expense by closing without requiring the investor to object. If the investor closed with one still unresolved, the agreement called for a lease amendment assigning the tenant the removal or insurance obligation and requiring indemnity for the property owner. Have the closing team specify which cure path applies and who will verify completion.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss a data center sale, lease or existing agreement
Sunland accepts data center property sale, lease and existing agreement assignment inquiries from owners and authorized representatives across the United States. Share the general location, proposed transaction and next decision date. Keep title commitments, notices and signed agreements for private follow-up.
Questions landowners ask
What if the investor misses the initial objection deadline?
Section 9.3(b) treats matters in the update as permitted exceptions if the investor fails to object in time. It separately preserves the contributing member’s mandatory removal obligations.
Does the owner have to cure every qualifying new exception?
Under the signed agreement the contributing member could elect to take no action, giving the investor a choice to waive the matter and proceed or to terminate. Check mandatory removal exceptions separately.
Does the public filing show that a new title exception was raised?
The filing establishes the signed procedure and describes a future closing. The reviewed records leave any actual title update, objection, cure or closing unverified.
Sources & further reading
Sources checked November 21, 2026. Section 9.3(b) redacts one criterion for a new exception to qualify. The reviewed records leave any actual title objection, election, cure, termination, lease amendment and closing unverified. Local rules and program details can change. Check the requirements for the actual project.