Identify the land and the proposed work
Gather the deed, survey, title materials and any easements or existing access agreements. With a qualified surveyor and project designer, distinguish the private parcel from WMATA property and any areas subject to another party’s rights. Show the proposed battery equipment, fence, access, utility work and temporary construction and staging areas on a concept plan. Identify work that may extend beyond the private property limit and any uncertainty about ownership or rights.
A property line on a preliminary map is a starting point, not proof of the legal boundary or permission to work across it. Ask the project team to check the whole construction footprint as well as the finished layout. Keep detailed plans and other sensitive materials within the appropriate review process.

Send an early concept to WMATA
WMATA says JDAC reviews projects adjacent to, on, over or under Metro Rail and Metro Bus property, facilities and operations. Its program page asks for a project introduction and supporting documents by email to JDAC@wmata.com. The requested material includes a short, detailed scope narrative, a site plan showing the proposed project, WMATA facilities and nearby cross streets, a location GIS map and full address, a zone-of-influence sketch prepared in accordance with the Adjacent Construction Project Manual, a milestone schedule and contact information. Have the qualified project team prepare the materials and consult the current program page for the complete list.
WMATA says it will acknowledge an inquiry within seven to ten business days and respond after a minimum of 30 business days. If it determines there is no impact, it will send a no-impact letter. If it determines there is an impact, the project moves to impact analysis and a JDAC construction engineer is assigned; additional information may be requested. Build time for further review and revisions into the schedule. A concept inquiry or a no-impact determination for one described proposal should not be treated as blanket approval for a changed project.
Separate review from rights to enter
Assign one party, typically the developer with its design team, to prepare and submit the inquiry, answer questions, pay agreed review costs and share correspondence with the owner. The parties should confirm the actual applicant and process with JDAC. The owner should provide available title and site records and authorize work on its own parcel only to the extent agreed in writing.
If surveys, construction, access or permanent improvements require use of WMATA property, identify the activity and area and ask WMATA what separate permission or real estate instrument is required. The program page provides a real estate permit application among its applicable documents. The developer and owner should agree who applies, who bears fees and conditions, and who obtains any other third-party rights. Neither a private option nor an agency review outcome alone grants entry or a permanent easement. Do not enter or conduct work until the necessary rights and authorizations are in place.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landTie the option to the actual scope and schedule
In a sale or lease option, attach a dated concept plan and describe the initial scope, submission responsibility, review budget and target dates. Require the developer to provide the owner with the JDAC response and material follow-up. Define an objective milestone for receiving the applicable written WMATA determination or other agreed review outcome, with a practical extension process if the agency needs more time and a clear consequence if the milestone is not met. Agency timing and the final outcome are outside either party’s control.
If the battery layout, access, utility route or construction area materially changes, require a revised plan and prompt notice to the owner. Ask JDAC whether the change requires an updated submission or further review, and set a new or extended milestone as the parties agree before affected work begins. Address responsibility for additional costs and termination or redesign if needed rights or approvals cannot be obtained. A sale, lease or assignment should also address consent, surviving obligations, restoration and the transfer or reapplication of any permissions as required by their terms and the issuing authority.
Prepare a land inquiry
Sunland welcomes land sale, lease and existing agreement assignment inquiries for battery storage nationwide. Share the location, acreage, current use, transaction interest and known property or access constraints. Provide surveys and agency correspondence privately when requested. WMATA review is separate from local land-use, building and fire approvals, utility interconnection and other applicable requirements.
Questions landowners ask
Does a private parcel beside Metro automatically need a particular permit?
Not necessarily. Submit the proposed scope to JDAC and ask what review and separate permissions apply to the actual work and location.
Does a no-impact letter authorize entry onto WMATA property?
Do not assume it does. Ask WMATA about any separate permission or real estate instrument needed for the proposed entry or use.
What if the project changes after the first inquiry?
Document the revised scope and plan, notify the owner and ask JDAC whether further submission or review is needed. The option can provide an agreed schedule and consequences for the change.
Sources & further reading
Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.