Florida landowner guide

How can a battery storage project take possession of a marina dry-storage yard?

A Florida landowner considering a battery energy storage system (BESS) sale or lease may have an operating marina storing customers’ vessels on the proposed site. A closing or lease commencement date does not itself clear the yard or give the landowner authority over the boats.

Could my land work?

Review the marina’s occupancy and customer arrangements, identify each vessel and the people with rights in it, and agree on a phased removal and possession plan. Keep the lift, haul routes and emergency access usable until the relevant boats leave. Resolve disputed charges or liens with Florida counsel; do not assume the landowner, operator or developer can move, sell or dispose of a vessel simply because the project needs the space.

Identify the operator, vessels and rights

Collect the land lease and amendments, renewal and termination provisions, storage agreements, site plan and available notices. Distinguish the landowner from the marina operator or tenant, the owner or authorized representative of each vessel, and any secured or other lienholder. The operator’s agreement to surrender the land does not alone establish authority to move customer-owned vessels or settle third-party claims.

With the operator, inventory each vessel by hull identification number where available, registration or documentation, location, condition and associated trailer or equipment. Record known owner contacts, storage terms, outstanding charges and claimed liens securely. Ask Florida counsel to review occupancy, notice, access, title and lien issues, including state and federal vessel records where applicable; do not assume the inventory establishes ownership or priority.

Illustration of a land parcel and surrounding landscape

Preserve a working marine operation during removal

Map the racks and stands, lift or travel-lift basin, lift clearance, launch and haul-out areas, staging space, washdown, gates and the route to the public road. Check vessel height and width, equipment capacity, turning radii, overhead and ground clearance, pavement loading, tides and scheduling with the operator and qualified haulers. A route drawn on a plan is insufficient if a lift or trailer cannot actually use it.

Sequence fencing, trenching, deliveries and construction around remaining operations. Agree on notice for entry, traffic separation, gate control, utilities, fire and emergency access, working hours and who pays for continued operation. Obtain permission for any temporary route or offsite staging and test its practical use before the original route is blocked. Coordinate destinations, receiving facilities, transport, insurance and required permissions with each owner or authorized representative; allow contingencies for weather, equipment failure and delayed moves.

Treat vessel liens as a separate issue

Florida Statutes § 328.17 provides a qualifying marina a possessory lien for specified storage, dockage, repair, preservation and related charges, and separately addresses certain abandoned vessels in wrecked, junked or substantially dismantled condition. Section 327.02 defines a marina for these purposes as a licensed commercial facility providing secured public moorings or vessel dry storage on a leased basis; it also includes an authorized vessel-manufacturer dealership for nonjudicial sale purposes. A bare landowner does not acquire those marina rights merely by owning the parcel. Whether this operator qualifies and whether a particular claim applies require a fact-specific review.

Section 328.17 prescribes a process for satisfying an applicable lien, including specified owner and lienholder notices and searches, timing, advertising and commercially reasonable disposition requirements. It also addresses redemption and lien priority; subsection (11) preserves prior liens perfected under state or federal law against a good-faith purchaser, unless otherwise provided by law. Ask counsel to evaluate each disputed vessel, charges and competing interests and arrange an appropriate resolution with affected parties. Neither an unpaid bill nor a project deadline is permission for self-help removal, sale or disposal. Marine vessel rights and procedures need their own review; do not substitute assumptions from vehicle towing or general storage guidance.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Accept the lift corridor before closing it

Divide the parcel into mapped areas with dates and conditions for surveys, limited entry and exclusive possession. State which vessels and equipment must leave each area, which lift and haul routes remain available, and who controls gates, maintains utilities and bears relocation costs. Set a process for delays, disputed boats and alternative staging, and address how incomplete handoff affects commencement, payment and construction. Have counsel fit these terms to the actual land and storage agreements.

Before fencing or trenching closes a haul corridor, the operator and project team should confirm that the last scheduled vessel for that phase has actually been launched or hauled away and that any vessels remaining can still reach the lift and road by an agreed usable route. Record the test or demonstration, lift clearance, gates and turning area, outstanding exceptions and who may authorize the corridor closure. Document vessel departure and receipt with the appropriate parties, and keep permissions, claim resolutions and signed area handoffs with the project records.

Sunland welcomes battery storage land sale, lease and existing project inquiries nationwide and may contract for a property and assign the agreement to a specialist. Share the county, approximate acreage, marina occupancy, expected timing and access constraints. An inquiry does not commit you or guarantee a project; share sensitive vessel and ownership records securely when needed.

Questions landowners ask

Can a landowner move stored boats when a BESS lease starts?

A project lease alone does not establish authority to move customer vessels. Review the operator’s and owners’ rights and obtain the required permissions for each move.

Does owning the marina land give the landowner a vessel lien?

Not merely by owning the land. Section 328.17 addresses a marina as defined in section 327.02; whether a person qualifies and has a particular claim depends on the facts.

When can the project close the lift corridor?

Use the agreed phased handoff conditions. Confirm the last scheduled launch or haul for that phase and test an agreed usable route for any vessels remaining before fencing or trenching blocks the corridor.

Sources & further reading

Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.