Idaho landowner guide

Should you extend a battery land agreement while a utility purchase is pending?

If a battery developer asks you to hold your Idaho land longer because a utility might buy the project, ask which deal steps have actually occurred. Then compare the proposed extension or payment date with the documents that govern those steps.

Could my land work?

Request the commission order, an explanation of the utility’s purchase option, and any notice or closing record the developer is relying on. At Crimson Orchard, the Idaho commission approved power and storage agreements and left the costs of a possible option exercise to a future review if the utility seeks recovery. Ask counsel to match the trigger in your land agreement to the evidence you can obtain.

Read what the commission approved

Ask for the Idaho Public Utilities Commission case number and the latest order for the project. In the Crimson Orchard case, the commission’s amended and restated Order 36881 approved Idaho Power’s power purchase agreement, energy storage agreement and the first amendment to each. Order 36932 later clarified how the commission would review costs for recovery through utility rates.

The commission excluded the costs associated with exercising a purchase option from its initial determination of which expenses could be presumed prudent. If Idaho Power elects to exercise a purchase option and later seeks recovery of those costs, the commission reserved full review of whether the costs were prudently incurred. Read the order for the scope of that decision, and ask for transaction records to establish any exercise or closing.

Illustration of a land parcel and surrounding landscape

Identify the event that affects your agreement

Ask the project team what the utility could acquire under the option and which rights in your property, if any, the purchase would affect. Ask who would remain responsible under your land agreement and what document would show any assignment or assumption. If the developer says the utility has exercised an option or has closed a purchase, ask for the relevant dated exercise or closing record.

If the developer cites future cost recovery as a reason for more time, ask it to identify the exact decision it expects, whether the request has been filed, and which transaction or payment term depends on it. Have counsel distinguish any condition in the signed documents from an assumption in the developer’s schedule.

Decide what to ask for in an extension

Put the existing land option or lease dates beside the proposed purchase and payment dates. For example, if the developer wants rent to start when it transfers the project to a utility, ask what you would receive while the land remains committed, how you would verify the transfer, and when the reservation would end if that transfer is delayed or falls through.

Have counsel review any proposed extension, consent or lease assignment. Identify who will update you, when the update is due, and what signed document or notice will show that the agreed milestone occurred. Keep the current agreement and any amendments with the records you used to make the decision.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Discuss your property or existing agreement

Sunland welcomes inquiries from owners and authorized representatives nationwide about selling or leasing battery storage property or assigning an existing agreement. Share the general property location, your role and the transaction you are considering. Keep signed agreements, purchase documents and private payment records out of the initial inquiry.

Questions landowners ask

How do I check whether the utility has exercised a purchase option?

Ask for the relevant option provision and the dated record showing exercise. If the developer reports a completed purchase, request the closing evidence that shows what transferred and when.

What did the Idaho commission decide about option costs at Crimson Orchard?

It left those costs outside the initial prudence finding. If Idaho Power exercises a purchase option and seeks cost recovery, the associated costs are subject to a full prudence review.

What if the developer wants the land held until a utility purchase closes?

Review the proposed extension with counsel. Decide what payment and progress records you would require, and check what the agreement says about the release of your land if the purchase is delayed or falls through.

Sources & further reading

Checked the Idaho Public Utilities Commission’s case record and both final orders on November 21, 2026. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in Idaho?Tell us about your land