First check whether the Act covers the project
Illinois’s Renewable Energy Facilities Agricultural Impact Mitigation Act uses its own definition of a commercial solar facility: generally a solar conversion facility of at least 500 kilowatts of nameplate capacity. The AIMA provisions address covered facilities on privately owned agricultural land under an underlying agreement. This threshold is not a substitute for the separate county siting law’s definitions or a finding that a particular project qualifies.
The Act excludes, among other things, land owned by the facility owner, certain facilities constructed or permitted before June 29, 2018, and certain customer-side facilities of 2,000 kilowatts or less intended primarily to offset that customer’s load. A facility seeking an extension of a county or municipal construction permit granted before that date is included in the definition. Section 15 also preserves underlying agreements entered before June 29, 2018. Ask counsel to examine project ownership, capacity, use, permit and agreement dates, and the effect of any later amendment or transfer. An outright sale to the facility owner can change the analysis.

Compare the actual AIMA with the lease
The AIMA is between the facility owner and the Illinois Department of Agriculture. Request the project-specific document, signature status, exhibits, lease or option, amendments and any separate waiver or work agreement. Identify the land and activities covered, including access and temporary work areas. Ask for a written explanation of each difference from the department’s standard solar form and how it affects your property.
The standard form says its actions may be modified through advance negotiation between landowner and facility owner, except sections 17.B through 17.F. Those exceptions address deconstruction timing, plans and financial assurance. Do not assume every standard is unchangeable, or that a lease clause labeled “standard” preserves the same protection. Ask counsel how the documents fit together, what a proposed change gives up and what survives assignment or termination.
For a qualifying project, the Act calls for the signed standard agreement to be submitted to the department at least 45 days before actual construction and a copy of the submitted or fully executed agreement to be given to the landowner at least 30 days before construction. The standard form also calls for incorporation into the underlying agreement. A submitted copy may not yet be fully executed: request the final signed version and all changes, and confirm the actual schedule.
Decide who should do repairs
The standard form permits the facility owner to negotiate for a landowner to perform actions the landowner wishes to do, with an offer of the area commercial rate for machinery and labor. Before accepting, define the work, materials, payment timing, access, documentation and how unexpected conditions or additional costs will be handled. Ask whether you have the equipment, time and insurance needed, and whether a qualified contractor should do the work instead.
The choice matters for drainage. Under standard section 6.G, the facility owner must correct qualifying failed tile repairs it made for one year after completion of construction or deconstruction, but is not responsible under that provision for tile repairs it pays the landowner to perform. Ask your attorney what responsibilities and remedies the actual agreements provide if your paid repair fails, causes a later loss or needs additional work. A commercial-rate offer alone does not answer those questions.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landMake the protections workable on your farm
Mark the project footprint, temporary routes, outlets and fields you will continue to farm on a dated map. Collect existing tile maps, drainage district information, repair invoices and photographs of wet areas; note gaps or uncertain locations. Involve your farm operator, who may know where a line was repaired or which entrance is needed at harvest.
The standard form addresses damage to surrounding drainage and restoration within the facility footprint after deconstruction. It also calls for as-built drawings of encountered tile, repairs and underground cable within 60 days after construction is complete. Ask who locates unknown lines, how damage is reported, who arranges prompt work, and who receives updated drawings. Compare the lease’s crop-loss and other damage terms with the AIMA rather than assuming one payment covers every loss.
Review proposed changes to wet-weather work, topsoil handling and access as well. Keep a construction contact, dated notices, photographs, repair records and copies of drawings with the signed agreements. Ask how the farm operator reports problems and how the parties document completion.
Follow the obligations through transfer and removal
The Act binds a subsequent facility owner to the AIMA. The standard form calls for the incoming owner to give written notice to the department, county and landowners within 90 days of transfer, with financial assurance and other AIMA terms applying to it. On a transfer, request the new responsible entity and contact, a list of open repairs, the current removal plan and evidence of assurance. Have counsel review the lease’s consent and assignment language and any continuing obligations.
Under the standard form, deconstruction assurance is phased: 10% of estimated costs by the first operating anniversary, 50% by the sixth and 100% by the eleventh, based on the applicable plan. Check the executed agreement, county requirements, estimate and actual security; the standard does not mean the full amount is funded on day one or guarantee that money will cover every loss.
Discuss your Illinois property
Tell Sunland the property location, approximate acreage, current farming use and whether you are considering a solar lease or sale. If you have an offer or AIMA, describe its status and any proposed repair arrangement or drainage concern. Sunland welcomes inquiries from owners and authorized representatives nationwide. An inquiry does not commit your land; your own advisers can review the documents and project-specific legal questions.
Questions landowners ask
Is the state template my project’s signed agreement?
No. Ask for the project-specific submitted and final executed AIMA, incorporated documents and negotiated changes.
Must I repair damaged tile myself?
The standard form allows negotiation for work the landowner wishes to perform. Review the proposed scope, payment and consequences of failed repairs before agreeing.
Does an AIMA guarantee all restoration costs will be paid?
No. Examine the actual obligations, available financial assurance and lease remedies with counsel; an agreement does not guarantee the responsible party’s solvency.
Sources & further reading
Statute and agency-linked standard solar AIMA checked November 19, 2026. The linked standard is version 8.19.19; no project-specific agreement was reviewed. Local rules and program details can change. Check the requirements for the actual project.
- Illinois General Assembly: Renewable Energy Facilities Agricultural Impact Mitigation Act, section 10
- Illinois General Assembly: Renewable Energy Facilities Agricultural Impact Mitigation Act, section 15
- Illinois Department of Agriculture: agricultural impact mitigation agreements
- Illinois Department of Agriculture: standard solar AIMA