Decide what can actually be offered
Mark occupied buildings, leased areas, storage yards, shared roads and the portion potentially available for sale or lease. Identify tenants, expiration dates and rights that could affect access. A project may need outside space for equipment, setbacks, construction and circulation as well as a building footprint.
If you intend to keep operating on the rest of the property, describe truck routes, parking, shared utilities and hours of operation. Ask whether a conceptual layout preserves those needs before agreeing to an exclusive option.

Collect records of past and present use
Gather available site plans, permits, prior environmental reports, information about tanks or known spills, and records of cleanup or ongoing monitoring. Do not assume an old report resolves current questions. Share known information accurately and ask a qualified environmental professional what additional work is appropriate.
EPA describes all appropriate inquiries as a process for evaluating environmental conditions and potential contamination liability. Depending on the transaction and circumstances, a buyer may seek a Phase I environmental site assessment and other review. Legal and technical advisers can explain the implications for the parties.
Treat existing infrastructure as evidence to investigate
Provide available electric bills, service agreements, equipment details and plans. A previous industrial load or nearby substation does not establish service for a new data center: the utility must assess a specific proposed load, upgrades, cost and timing.
A building also needs assessment for the proposed configuration, including structural condition, flood and drainage concerns, fire protection, communications, cooling and local approvals. Reusing a building and clearing a site are different proposals with different costs and permissions.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCompare the proposal with continued use
Ask for a plan showing what is included in the sale or lease, which facilities would be removed or shared, and how access and utility rights affect retained land. Discuss responsibility for investigation, remediation, demolition, permits and restoration with your advisers.
Compare the price or rent alongside contingencies, option length, extension rights and timing. If environmental or service findings make the project infeasible, ask what happens to the agreement and whether any investigation results will be shared.
Questions landowners ask
Can an operating industrial property be considered?
Possibly. Describe the area available, current occupants and operations that must continue; compatibility depends on a specific layout and agreement.
Does past industrial use rule out a data center?
Not by itself. Environmental conditions and the proposed design need qualified, site-specific review.
Must I pay for a new environmental study before contacting Sunland?
No. Share available records and known history. Later studies and their cost can be addressed in a proposal.
Sources & further reading
Sources checked 2026-11-15. Local rules and program details can change. Check the requirements for the actual project.