Kentucky landowner guide

Who decides what stays when a Kentucky solar project is removed?

A Kentucky solar lease may outlast your ownership of the land. Before promising a buyer how the site will be returned, check the current decommissioning plan, which equipment belongs to the project and which choices Kentucky law gives the landowner at the time of decommissioning.

Could my land work?

Collect the signed lease, current plan, certificate conditions and equipment map. Check with Kentucky counsel which requirements apply to your project and what the landowner at decommissioning can request about removal or retention. Give the buyer the latest records and document how the operator will reach the owner when those choices need to be made.

Check which rules apply to the project

Kentucky’s July 2026 amendments changed the minimum decommissioning plan requirements for covered merchant generating facilities. Ask counsel to review the project’s certificate, local approvals, plan and lease dates and confirm which requirements apply. Kentucky law gives certain local decommissioning requirements priority, so obtain the latest filed plan, applicable local approvals and any later conditions or updates. The published state regulation still describes removal to three feet unless the landowner requests otherwise. Ask the Kentucky Energy and Environment Cabinet how the current statute and project conditions apply to your plan.

In the July 2026 Mayfield Solar order, Kentucky’s Siting Board discussed a filed plan that described three-foot removal and directed that the plan submitted under KRS §278.710(8) include all project components. The order also addressed individual lease restoration commitments. For your site, compare the latest agency records with the lease and the plan the developer is using.

Illustration of a land parcel and surrounding landscape

Review removal, depth and retention separately

Under KRS §278.706(2)(m), the current minimum-plan provisions address what stays or goes at the end of a covered facility’s useful life. They refer to requests by the landowner at the time of decommissioning. A different removal depth for buried components requires agreement between that landowner and the applicant at that time.

Ask the project company to identify equipment covered by the plan and any utility-owned facilities or separately granted easements. Review which equipment can be disconnected, removed or left in use, who can authorize the work and who would maintain anything that stays. Confirm the applicable restoration terms for the affected area.

Site itemWhat the current minimum plan addresses
Above-ground project facilitiesRemoval unless the landowner at decommissioning requests otherwise.
Underground components and foundationsRemoval unless that landowner requests otherwise. Components removed under this provision are removed in full unless the owner and applicant agree to a different depth at decommissioning.
Interconnection or other facilities covered by the retention provisionLeft in place for future use unless the landowner at decommissioning requests otherwise.
Ground and soilRestore the land to a state substantially similar to its condition before construction.

Record the owner’s requests and any agreement

The statute calls for communication with affected landowners at the end of the facility’s useful life and requires the applicant to incorporate the specified decommissioning provisions into its leases with landowners. Check the lease and plan for how to make and document a request. Identify the component and location, what should stay or go and who should receive the written request.

Keep any agreement on a different removal depth with the map and the final plan. Ask the project company to confirm receipt and document how a request is addressed. Requests beyond the statutory minimum and the lease requirements may be accommodated at the sole discretion of the applicant or its successor or assign.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Give the buyer the records and notice details

Before selling, list the plan and lease provisions in the closing file, identify any requests already made or questions still open, and check where notices go after closing. Give the buyer the latest equipment map, plan, certificate conditions, local approvals and separate utility easements. Ask counsel to confirm how the documents address decisions that will be made at decommissioning.

If you are negotiating a lease now, identify how the operator will keep current owner contacts, obtain later instructions and share any plan updates. Sunland welcomes nationwide inquiries from owners and authorized representatives about solar land sales, leases and assignments of existing agreements. Share the approximate location, the proposed transaction and whether the project already has a removal plan. Keep signed agreements and detailed site records for private review.

Questions landowners ask

Does the July 2026 law decide what happens under my older solar lease?

Ask Kentucky counsel to review the dates, lease provisions, certificate and local requirements. Compare them with the current statute and the latest project plan before making a promise to a buyer.

Can the owner ask that an interconnection facility be removed?

The current statutory plan provision allows a request by the landowner at decommissioning. Confirm which facility the provision covers and review its ownership, utility rights and approvals before making the request.

Who agrees to a different depth for removing buried components?

Under the current provision, the landowner and applicant agree on a different depth at the time of decommissioning. Document the components, agreed depth and location in the applicable project records.

Sources & further reading

Kentucky statutes and the Mayfield order were checked November 20, 2026. The order records project conditions. Whether a landowner made a request or the project implemented any removal or retention remains unverified. Local rules and program details can change. Check the requirements for the actual project.