Find the permit and identify when the pause began
This rule concerns utility-scale battery projects covered by Linn County’s Unified Development Code. Ask the zoning office to confirm which permit and approved decommissioning plan apply to the site. Request dated records of when the system last stored energy or when substantial construction or repair work stopped, and ask which event the county uses for the project.
Section 107-117(j)(8)(f) gives the permit holder one year to complete decommissioning after a continuous year with no energy stored or after substantial construction or repair work has been discontinued for one year. The permit holder must complete the work in accordance with the approved decommissioning plan. Ask the county to confirm the trigger date and completion date for the actual project.

Check whether the county extended the initial period
The ordinance gives the zoning administrator discretion to extend the one-year period that triggers decommissioning if the applicant shows ongoing commitment. It lists making lease payments and documenting ongoing maintenance or repairs as examples. If the operator cites those records, ask whether the applicant requested an extension and whether the administrator granted it.
Ask the county how it documented its decision and which dates it applies. A copy of the request or a record of payment can support your review. Use the county’s determination to establish whether the initial period was extended and when decommissioning would then be due.
Assign both notices and check the lease dates separately
The ordinance calls for the landowner or tenant to notify the zoning administrator when the project is discontinued and again when decommissioning is complete. Confirm with the county how it wants to receive the notices. Have the parties agree who will send each one and who will keep the dated notice and delivery record.
Put the county’s dates beside the lease provisions for rent, equipment removal and return of possession. If the operator is still paying rent while asking for more time, have counsel review what those payments mean under the lease and whether the owner needs to agree to any change. Before agreeing to a handback or sale date, ask which work and records must be delivered under the approved plan and your agreement.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your property or existing agreement
Sunland welcomes inquiries from owners and authorized representatives nationwide about selling or leasing battery storage property or assigning an existing agreement. Share the general property location, your role and the transaction you are considering. Keep signed agreements, operating records and payment statements out of the initial inquiry.
Questions landowners ask
Does continued rent establish an extension?
Lease payments are one type of evidence an applicant can provide. The zoning administrator decides whether to extend the initial period. Ask the county for the status and applicable dates.
Which period can the zoning administrator extend under this rule?
The ordinance addresses an extension of the initial one-year period that triggers decommissioning. Once the trigger applies, the ordinance gives the permit holder one year to complete the work. Ask the county how it applies those dates to the permit.
Who notifies the county when the project ends?
The landowner or tenant notifies the zoning administrator when the project is discontinued and again when decommissioning is complete. Confirm who will send each notice and keep a copy.
Sources & further reading
The recorded ordinance and current Linn County battery storage guidance were checked November 21, 2026. Local rules and program details can change. Check the requirements for the actual project.