Confirm the permit and effective date of the change
Resolution 2026-4 took effect February 17, 2026. Its applicability section covers battery energy storage facilities with at least 1 megawatt of nameplate capacity that were permitted and installed after the effective date. Start with the permit number, site address or parcel number, reported capacity and permit and installation dates. Ask the County which rules and permit conditions apply if the project was approved under an earlier permit.
Identify what changed and when. The project buyer, land buyer and incoming operator can be different parties. Ask the County how § 1-108 applies if only the operator changes or if the land sells while the same company owns and operates the batteries. For a change still being negotiated, ask who will handle notice and how that person will document the effective date and delivery.

Check the notice and who received it
Section 1-108 requires the written notice to include the chief executive officer’s name, company phone number and company address for both the subsidiary and its parent company. Ask the County what it expects if the incoming company has no parent. Save your copy and any mailing envelope or email with its date. Use the notice and permit record to verify the new company’s identity, then ask for the day-to-day contact for access, repairs or operating questions.
If you own nearby property, use the Assessor’s parcel map or records search to identify your parcel and compare it with the project site. Give Planning and Zoning the parcel number and ask whether your property falls within the project’s notice recipients. If you received no notice, ask what records show the notified parcels, dates and delivery.
Verify the written assumption and current approvals
When the battery project or the host property changes owners, § 1-108 provides for the special use permit to remain in effect if the successor owner or operator assumes all obligations of the special use permit and decommissioning plan in writing. Ask the County whether it has the signed assumption available for review and confirm that it names the successor and covers the current permit and plan.
The same section says that failure to provide the required written notice on time voids the special use permit and the project’s other local approvals. Reinstatement is subject to the review and approval process for a new application and any required fees. If notice appears late or incomplete, ask the County for the current status of the approvals and any reinstatement decision. The new owner is responsible for obtaining necessary building permit extensions.
| Record to ask for | What to verify |
|---|---|
| Special use permit and current decommissioning plan | The covered facility and the obligations the successor would assume. |
| Dated transfer or operator change record | The parties involved, what changed and when it took effect. |
| Written notice and evidence of delivery | The named companies, required contact details, recipients and dates. |
| Signed assumption and County approval record | Who assumed the permit and plan and the County’s current status for the approvals. |
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landReview your agreement before signing a consent
If you host the project, give your adviser the signed lease or option, amendments, any guaranty and the proposed assignment, consent or release. Identify who owes the next payment, who must repair existing damage and who owes private restoration work. Ask whether your signature would release an outgoing tenant or guarantor. If the transaction is pending, record who will supply the written assumption and notice evidence, and by when.
Owners and authorized representatives anywhere in the United States can contact Sunland about a battery storage property sale, lease or existing agreement. Start with the general location, your relationship to the property and the type of ownership or operator change. Keep signed agreements and supporting records for private follow-up.
Questions landowners ask
Does the Logan County rule include neighboring landowners?
Yes. Section 1-108 includes neighboring landowners among the written notice recipients for a covered change. Give Planning and Zoning your parcel number and ask which parcels were included and what evidence establishes delivery.
Who owes rent after the change?
Check the signed land agreement, any assignment and any guaranty with your adviser. Ask who owes the next payment and what the proposed consent would do to the existing parties’ obligations.
Sources & further reading
Logan County’s signed resolution, current zoning page and Assessor resources were checked November 22, 2026. Confirm the project’s permit, notice recipients and approval status with the County. Local rules and program details can change. Check the requirements for the actual project.