Maryland landowner guide

Can I use an expiring Maryland CREP buffer for solar access?

A Maryland landowner considering a solar sale or lease may see one Conservation Reserve Enhancement Program (CREP) buffer contract approaching expiration and expect a road or cable route to become available. First identify every overlapping or stacked strip and any separate permanent easement. The first expiration may not end the need to maintain the entire buffer.

Could my land work?

Gather all federal CREP contracts, amendments, strip maps, expiration dates and conservation plans, along with any recorded easement deed and complete exhibits. Maryland Department of Agriculture (MDA) guidance says an owner may decline to re-enroll the first expiring stacked strip but must maintain the whole buffer until the other contracts expire. A separate, voluntary Maryland Department of Natural Resources (DNR) perpetual easement can continue after federal contract expiration and may cover more than the contracted strips. Compare the actual records with the proposed solar footprint, roads and cables, and ask the relevant agencies and counsel before promising access or disturbing the buffer.

Map every strip and its contract date

Obtain each signed federal CREP or CRP contract and amendment, enrollment and practice maps, conservation or forest stewardship plans, maintenance requirements, payment records and correspondence. List each strip, practice, acreage, contract holder and start and expiration date. Have the local USDA Farm Service Agency (FSA) office and soil conservation district help reconcile the records and identify the current practice requirements. A single parcel can have adjacent stacked strips with different contract dates.

MDA says each stacked strip must be re-enrolled separately; when re-enrolling additional strips, an owner can request a shorter contract to align expiration dates. The owner may choose not to re-enroll the first expiring strip, but MDA says the entire buffer must remain until the other contracts expire so the outer buffer continues to meet practice requirements. For example, an inner strip expiring this year is not automatically an open corridor for construction while an outer strip remains under contract. Ask FSA and the district how the specific layout and proposed work are treated; do not infer permission from a date alone.

Illustration of a land parcel and surrounding landscape

Look separately for a permanent easement

A federal CREP contract and a DNR Conservation Reserve Enhancement Permanent Easement are distinct commitments. DNR describes the latter as a voluntary, perpetual recorded agreement available to owners with an existing federal CREP or CRP contract and installed practices. If granted, its conservation obligations continue after the federal contract expires and bind later owners. Not every CREP contract means an owner granted a permanent easement.

Search county land records for the actual deed, amendments, legal description, plats and all exhibits, and compare them with the conservation or forest stewardship plan. DNR’s August 2025 FAQ describes possible contract acres, qualifying adjoining match acres and additional acres in an easement. Thus the recorded boundary may extend beyond the federal buffer. Verify the specific land and reserved rights in the deed instead of assuming the easement follows the contract map or covers the whole farm.

Test the proposed solar route against both layers

Draw the proposed panels, fencing, construction and permanent roads, cable and utility routes, staging, grading and drainage on the same map as each strip and any easement boundary. Include access from the public road and routes to the interconnection point, not just the panel area. An apparent crossing of a narrow buffer can control access to otherwise usable acreage.

DNR says permanent easements typically restrict development, roads and utilities, and their terms are property-specific. Ask FSA and the soil conservation district about active federal contracts and practice compliance; ask DNR or the identified easement holder about the recorded deed, proposed crossings and any applicable review. Obtain their written guidance and any required approvals before work or a binding access commitment. Expiration of a federal contract alone does not authorize a road, trench or cable, and other property rights and permits may also matter.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Put the records and timing into the transaction

Share the map and documents privately with the prospective buyer or tenant and qualified counsel. Identify who will confirm boundaries, seek agency guidance, pay for surveys or design changes and maintain required vegetation. Consider alternatives outside restricted land, including a different entrance or utility alignment. Do not promise that an agency will approve a crossing or that an easement can be changed.

In a sale or lease, counsel can address the exact land and access rights offered, continuing conservation duties, review and approval conditions, possession timing and the outcome if a route is unavailable. Keep maintenance and agency access workable during diligence and throughout any lease. A closing or possession date tied only to the first federal expiration may be premature.

Start a solar land inquiry

Owners and authorized representatives can share the parcel location, approximate acreage, present use, road access, nearby electrical infrastructure, desired sale or lease and known CREP or easement restrictions. Gather the contracts, plans, deed and exhibits for confidential diligence rather than relying on a summary map.

Sunland considers solar land opportunities across the United States. Sunland may put a parcel under contract and subsequently assign that contract to a specialist developer. Owners with existing project agreements are welcome to inquire. Site suitability, transaction timing and approvals are not guaranteed; consult the relevant agencies and qualified counsel about the property.

Questions landowners ask

Can I use the first expiring strip for a solar road?

Do not assume so. MDA says the entire stacked buffer must be maintained until the other contracts expire, even if the first strip is not re-enrolled. Check the actual contracts and proposed activity with FSA and the soil conservation district.

Are all Maryland CREP buffers permanent?

No. A federal CREP contract has a term; a separate DNR perpetual easement is voluntary and, if granted, continues after contract expiration. Check the county land records and the actual deed.

Can a permanent easement cover land beyond the federal buffer?

Yes. DNR describes qualifying match acres and additional acres that may be included. The recorded deed and its exhibits establish the particular easement boundary and terms.

Does the final contract expiration automatically allow solar access?

No. A recorded easement or other restrictions may remain, and the proposed road or cable may require review or approvals. Confirm the actual rights and conditions before committing to access.

Sources & further reading

Sources checked 2026-11-17. Local rules and program details can change. Check the requirements for the actual project.