Locate the device and establish who owns it
Obtain the cross-connection survey, approved design and installation records, device permit, recent inspection and maintenance reports, and water and fire service drawings. Identify the device, its location, the service and properties it protects, the public water system and the owner or agent in its records. Compare those records with the deed, utility easements, lease and proposed battery footprint. An existing fire service may run outside the land being conveyed or supply a building retained by the seller.
A battery project does not by itself establish that a backflow device is required or that ownership changes. Determine whether the transaction transfers the device itself, merely transfers land around it, or leaves it with the existing facility. Ask the water system how it identifies the responsible owner and what documentation it needs; have counsel resolve conflicting ownership or access records before closing.

Distinguish ownership notice from removal notice
Under 310 CMR 22.22(13)(j), the owner or owner’s agent must notify the public water system in writing no later than 30 days before a change in ownership. The notice must include at least the new owner’s name and address and documentation proving the ownership change. The regulatory definition of owner includes a person maintaining a cross-connection installation or owning or occupying premises where cross connections can or do exist; it is not limited to the holder of title to a device. Plan the notice and supporting documents before closing; confirm with the water system what proof and delivery method it accepts.
Section 22.22(13)(i) separately requires written notice to the public water system no later than 30 days before removal from service of any permitted device. The notice must state the reason and indicate whether the cross connection has been eliminated. A change in ownership is not itself a removal notice, and removal should not be assumed to be permitted simply because a transaction closes. Coordinate any proposed service change with the water system and qualified professionals.
Protect shared fire service and access
Map the fire line, valves, device, meter, access doors and routes alongside the battery equipment, fencing, construction staging and emergency access. Confirm which facilities depend on the line and whether work could interrupt service. Section 22.22(13)(e) requires approval from the head of the fire department before a device on a fire protection system is overhauled, repaired or replaced. Discuss any proposed shutdown, relocation or redesign with the water system, fire officials and appropriate licensed professionals before changing the service; do not rely on an easement sketch alone to establish that the system will work.
The regulation requires the owner or agent to provide labor as necessary for inspection and testing and to maintain specified spare parts and special tools on the premises. Document who can enter, escort testers, provide workspace and utilities, maintain equipment and restore access after work. Allocate costs and notice obligations in the transaction documents, without assuming a private allocation changes regulatory duties.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landChoose terms that fit the transaction
For a partial sale, describe whether the device and service remain with the seller or transfer, and secure recorded access and service rights where needed. For a lease, identify the owner and operator responsible for notices, tests, repairs and uninterrupted access throughout the term and after expiration. For an assignment, check consent rights and ask the water system and counsel whether the transaction changes ownership under the regulation and what notice is needed.
Make closing or construction milestones conditional on resolving records, access, service continuity and any required approvals. Provide for inspection and repair costs, cooperation with the water system, and restoration or an approved replacement when the battery project ends. MassDEP’s current forms page says its BRP WS 09 application is no longer required and directs applicants to the local water authority for installation plan submission instructions; do not infer that no local review is needed.
Sunland reviews battery storage land opportunities nationwide. An owner or authorized representative can submit the location, approximate acreage and known shared water or fire-service issue; records can be shared privately if requested.
Questions landowners ask
Does selling the land automatically transfer a permitted device?
Not necessarily. Review title, device and service records and confirm the ownership and responsibilities with the public water system.
Is the 30-day ownership notice the same as a removal notice?
No. The regulation separately requires advance written notices for a change in ownership and for removal from service, each with different information.
Can a battery fence block the existing device?
Plan access before construction. The owner or agent must provide labor as necessary for inspection and testing; the parties should also secure practical access rights and coordinate with the water system and fire officials.
Sources & further reading
MassDEP’s 310 CMR 22.22 cross-connection regulations, forms and public water system guidance checked November 16, 2026. Confirm current requirements and local procedures with the public water system; the posted regulation is an unofficial version. Local rules and program details can change. Check the requirements for the actual project.