Find the adder in the project’s records
Ask for the solar project’s current Statement of Qualification and the compensation record or calculation showing the energy storage adder. Confirm that the project uses SMART 3.0. Under 225 CMR 28.13(3)(e), the energy storage adder is a variable addition to the solar unit’s base compensation rate for a qualifying paired system. The project’s contract and records can show whether that adder is part of the payment forecast you received.
SMART 3.0 uses the seasonal peak periods defined in the Clean Peak regulation. The payment at issue here is the SMART adder. If the offer also includes Clean Peak certificate revenue, ask the developer to identify that amount separately and explain which proceeds your agreement uses.

Use the defined peak periods to check the outage record
Under section 28.07(5)(e)1.c.i, the paired battery generally must be online and able to discharge at least 85% of the time during the summer and winter peak periods. Participation in a demand-response or grid-services program can satisfy the requirement for either or both periods. For periods without that participation, the project must demonstrate compliance to the Department of Energy Resources.
Under 225 CMR 21.02 and 21.05, both peak periods run from 4 to 8 p.m. on business days. Summer runs May 15 through September 14. Winter runs December 1 through the last day of February. Business days exclude weekends and state and federal legal holidays. Ask the project team to show how it assessed the outage against the applicable period and how it is demonstrating compliance.
If the battery is decommissioned or nonfunctional for more than 15% of either defined peak period, the department can end the solar unit’s eligibility for the storage adder. Ask whether the department has made a determination for this project and which period it covers. If a battery replacement is planned, ask the project team what confirmation it will seek about continued eligibility.
Check which payments the lease ties to the adder
For example, your agreement might provide fixed rent and a separate share of the project’s actual storage adder receipts. Ask counsel to identify which amounts the lease makes dependent on those receipts and how it handles periods when the adder changes. Check the actual compensation statements and any agency decision before agreeing to a revised payment.
If the developer proposes new terms, ask who must tell you about a change in adder status, which records you will receive and when, and how the parties will reconcile payments for the affected period. Keep the qualification, agency correspondence and payment records with the final land agreement.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDiscuss your property or existing agreement
Sunland welcomes inquiries from owners and authorized representatives nationwide about selling or leasing battery storage property or assigning an existing agreement. Share the general property location, your role and the transaction you are considering. Keep signed agreements, private operating records and compensation statements out of the initial inquiry.
Questions landowners ask
Does a battery outage automatically end the SMART storage adder?
The rule gives the Department of Energy Resources discretion to disqualify the solar unit from receiving the adder in the stated circumstances. Ask for the project’s compliance record and any determination the department has issued.
Which outage hours matter for the SMART 3.0 availability requirement?
The rule uses the defined summer and winter peak periods. Ask the project team to show which business days and hours apply and whether the system relies on program participation for the applicable period.
Does losing the adder change the rent in my lease?
Check the private payment terms with counsel. A share of actual adder receipts and fixed rent can have different payment terms even when both are in the same lease.
Sources & further reading
Current published Massachusetts regulations and the SMART 3.0 tariff status checked November 21, 2026. Local rules and program details can change. Check the requirements for the actual project.