Identify what the developer wants to do before closing
Ask the developer to mark each proposed early activity and its start date on the site plan. Give counsel the proposed entry agreement, lease or purchase contract, and any plan to turn over keys, fenced areas or control of the yard. Ask which activities are needed to conduct the BEA and which could amount to occupancy under Part 201.
If you agree to allow the BEA work first, have the access agreement describe the environmental work, where it can happen and when the permission ends. Set a separate written milestone for staging, grading, trenching or taking control of any part of the site. If entry has already occurred, give counsel the actual activity dates and records so they can assess the deadline before you make another commitment.

Give the environmental professional enough time to finish the report
For the Part 201 BEA route under MCL 324.20126(1)(c)(i), the assessment must be conducted before or within 45 days after the earliest purchase, occupancy or foreclosure date. EGLE explains that this includes finishing the inquiry, any field work and lab analysis needed for the assessment, and writing the report. Ask the environmental professional when each step can finish before you agree to a possession date.
The same provision gives the owner or operator six months from that earliest date to provide the BEA to the Michigan Department of Environment, Great Lakes, and Energy (EGLE) and subsequent purchasers or transferees. Confirm who will submit it in EGLE’s Remediation Information Data Exchange (RIDE) and keep the agency’s receipt or confirmation that the filing is complete. If another transfer is planned, have counsel check what must be delivered before it closes. If a deadline may already have passed, ask counsel whether to seek EGLE’s determination under section 20126(1)(c)(ii) that missing the time frame was inconsequential.
Confirm who will own or operate the site after an assignment
Give the environmental professional any existing assessment, sampling records, EGLE correspondence and recorded restrictions. EGLE accepts public-records requests for existing BEAs. Match the records to the battery premises, temporary work area, entrance and cable routes. The professional can advise whether the property or relevant portion meets Part 201’s definition of a facility and whether the BEA process applies.
If the original buyer or tenant expects to assign the deal, ask which entity will acquire or occupy the property and when. EGLE says the liability protection of an original BEA submitter does not transfer to a successor. A new owner or operator seeking protection through a BEA should arrange its own assessment and disclosure based on its own dates. Ask counsel to review any statutory exception for the specific party and use before relying on it.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landDecide when the site can be handed over
Ask the environmental professional what due care requires for the battery layout, including whether trenching or road work could disturb a cap or expose people to contaminated soil. Part 201 requires covered owners or operators who know the property is a facility to prevent worsening contamination, address unacceptable exposure and respect applicable land-use restrictions. A BEA addresses eligibility for protection from cleanup liability for existing contamination. It leaves due-care obligations and potential liability for releases the party causes in place.
Before agreeing to early possession, decide who pays for the environmental work, who handles any restrictions on the battery layout, and whether you will postpone turnover if reports or plans are incomplete. If you are considering a battery storage land sale, lease or assignment, share the property location, your role and the requested possession date with Sunland. Owners and authorized representatives can inquire nationwide. Keep environmental reports and agreement exhibits available to share privately when requested.
Questions landowners ask
Does access to take BEA samples start the 45-day period?
Section 20126 excludes assessing the property to conduct a BEA from occupancy. Have counsel review any other activity planned during the visit and track whether purchase, actual occupancy or foreclosure occurs first.
Can the next battery operator rely on the prior tenant’s BEA?
The prior report can inform the new assessment. EGLE says the original submitter’s liability protection does not transfer. Ask the incoming party’s advisers to review its own deadlines and whether it needs a BEA.
Can a BEA be finished before the buyer takes possession?
Yes. Have the buyer’s environmental professional schedule the inquiry, any required sampling and analysis, and the completed report before the earliest relevant deal date when feasible.
Sources & further reading
Sources checked 2026-11-19. Local rules and program details can change. Check the requirements for the actual project.