Identify the drain and its legal right-of-way
Start with the deed, title commitment, recorded easements, survey and any drainage plans or notices. Ask the county drain commissioner whether the feature is an established district drain, whether it is administered by an intercounty drainage board, and what plans, right-of-way documents and maintenance records exist. A private farm tile is not automatically a district-acquired right-of-way; a line on a general map does not by itself establish the easement’s location or terms.
Have a surveyor and drainage engineer compare the legal records with the visible ditch, covered drain, field conditions and maintenance history. Request missing records and resolve discrepancies with the responsible agency before the developer treats the corridor as usable. The width and extent must be established for this property rather than assumed from another site.

Test the battery layout and construction route
Put the proposed fence and gates, battery pads and foundations, buried cables, road, grading, crane paths and temporary staging areas on the same drawing as the drain and right-of-way. Show how equipment would enter, turn, excavate, deposit material and leave during future inspection or repair. A cable crossing may be underground while a fence or pad prevents the machinery needed to reach it.
Under Michigan Drain Code section 85, an owner may use land occupied by a district-acquired right-of-way for an open or covered drain only consistently with the district easement. A use that interferes with drain operation or increases the district’s cost of its work is inconsistent. Ask the commissioner or board to review the actual plan and identify the applicable permissions, design conditions and maintenance access. Do not assume every crossing follows one permit process or that a requested crossing will be approved.
Separate a crossing from a proposal to alter the drain
If the proposed footprint depends on moving, tiling or covering a drain, raise that proposal expressly with the agency and a qualified engineer before relying on the layout. Owner and developer agreement alone does not authorize the work. Section 425 addresses more than one situation and is not a general road or cable crossing permit.
For additional drainage, section 425 describes a district landowner petition to connect an open or closed drain to a regularly established drain, including written consent from owners of land the proposed drain would traverse before permission is granted, and agency conditions and petitioner expense. Separately, a person through whose land an established open drain runs may request in writing to tile and cover it at that person’s expense. The commissioner may grant the request and prescribes tile size; a permit to tile or crock an established drain cannot decrease its established area. Ask the agency which process, if any, fits the proposed work and what other approvals are necessary.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landBudget for access, changes and restoration in the deal
Before signing, compare the agency’s direction and the revised drawing with the option, lease or sale documents, title exceptions and farm tenancy. Ask who pays to redesign the project if the proposed road or cable cannot be used, who obtains approvals, and whether the owner can approve a material relocation. Budget for drain protection, construction damage, emergency access and restoration as well as the possibility of interrupted farm or project operations.
Specify who maintains gates and roads, how the district can enter, how damage is reported and repaired, and who bears costs if equipment must be moved for drain work. Have Michigan counsel check that private promises remain enforceable against the appropriate parties and successors under the actual agreement. A lease or sale does not displace the district’s rights, and the developer’s promise to seek approvals is not itself agency approval.
Bring the decision forward
Ask for a current plan, an agency contact and written direction, an estimated cost and schedule for outstanding engineering and approvals, and a clear decision date before committing the land. Keep the final survey, correspondence, permits and restoration commitments with the transaction records. Recheck the plan if the fence, cables or access route changes.
Sunland welcomes land sale, lease and existing agreement inquiries nationwide, including Michigan battery storage sites. Share the approximate location, acreage and the drain or access question. Sunland may contract and then assign an agreement to a specialist, subject to the actual agreement terms; review those terms and the drainage documents with your own advisers.
Questions landowners ask
Can a battery access road cross a county drain right-of-way?
It depends on the district’s acquired rights, the proposed design and applicable agency requirements. Map the actual crossing and obtain project-specific direction before committing to it.
Does section 85 apply to every farm tile?
No. Section 85 addresses land occupied by a right-of-way acquired by a district for an open or covered drain. Determine the drain’s status and obtain the applicable records first.
Can an owner cover an open drain to make room for equipment?
Section 425 provides for a written request to the commissioner in the circumstances it describes, at the requester’s expense. The commissioner may grant the request and prescribes tile size; the statute limits reduction of the established drain area. Obtain the agency’s direction and applicable approvals before work.
Will the battery lease settle maintenance access?
A private agreement can allocate duties between its parties, but it does not itself change district rights. Compare the agreement and final layout with the agency’s requirements and actual easement.
Sources & further reading
Sources checked 2026-11-18. Local rules and program details can change. Check the requirements for the actual project.